EPP to extend Eagle Ford crude oil pipeline

Christopher E. Smith
OGJ Pipeline Editor

HOUSTON, May 6 -- Enterprise Products Partners LP plans to build an 80-mile extension of its 350,000-b/d Eagle Ford shale crude oil pipeline, allowing it to serve growing production areas in the southwestern portion of the play. The 200,000 b/d Phase II project would originate in Wilson County, Tex., at the terminus of Enterprise's previously announced 140-mile Phase I segment (OGJ Online, Sept. 30, 2010), and extend to a site near Gardendale, Tex., in La Salle County, where a new 500,000 bbl central delivery point is planned.

Phase I is on schedule to begin service by second-quarter 2012, according to EPP, with Phase II set to commence operations in first-quarter 2013. The roughly 220-mile pipeline system will provide Eagle Ford producers with access to the Texas Gulf Coast refining complex through EPP’s Sealy, Tex., delivery point. The Sealy facility interconnects with its Rancho Pipeline and feeds into EPP’s new ECHO crude oil storage terminal being constructed along the Houston Ship Channel in southeast Harris County, Tex. (OGJ Online, Nov. 11, 2010).

The Phase II extension is anchored by a 10-year, 100,000 b/d shipping agreement with Chesapeake Energy Marketing Inc., a subsidiary of Chesapeake Energy Corp. EPP said, including the Chesapeake agreement, it now has producer commitments for 320,000 b/d under 10-year contracts.

About 165 rigs are working in the Eagle Ford shale, having drilled more than 1,200 wells, Enterprise said. Current production from the play is roughly 100,000 b/d. With more than 2.5 million acres under lease and potentially 15,000 wells to be drilled over the production life of the Phase II service area (based on EPP’s research and information it obtained from producers), the company expects development activity in this region of the Eagle Ford shale to remain brisk.

Estimates provided by producers also suggest that up to 3 billion bbl of crude oil are recoverable in the southwestern region of the play, EPP said.

Contact Christopher E. Smith at chriss@ogjonline.com.

Related Articles

US gas reserve growth in 2013 was robust, AGA estimates

04/17/2014 US natural gas producers added more than 35 tcf of reserves in 2013, the American Gas Association said in its latest annual preliminary estimate ba...

Industry improves public perception through outreach, education

04/16/2014 Public relations experts shared their thoughts on how the oil and gas industry can improve its image, and judges from two Texas counties spoke abou...

Energy reform could unlock Mexico's shale resource potential

04/16/2014 The oil and gas industry is watching with great interest as energy reforms unfold in Mexico. The country has taken the first steps toward opening i...

Port Corpus Christi emerges as a growing transportation and storage hub for crude oil from Eagle Ford shale

04/16/2014 Port Corpus Christi has emerged as a coastal gateway for crude produced in the Eagle Ford shale, with roughly 16.4 million bbl of crude moving out ...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected