InterOil moves ahead to build floating LNG

By OGJ editors
HOUSTON, Apr. 12
-- InterOil Corp.’s InterOil and Pacific LNG Operations Ltd. have agreed with Samsung Heavy Industries and FLEX LNG Ltd. to move ahead with construction and operation of a 2 million tonne/year (tpy) floating LNG processing vessel (FLNG). The agreements are conditional upon Flex shareholder approval and final investment decision (FID).

The FLNG project is part of proposed infrastructure to liquefy natural gas from onshore Elk and Antelope gas fields in the Gulf Province, Papua New Guinea, in line with preliminary arrangements with Energy World Corp. and to link with InterOil's proposed condensate stripping plant. That plant is being pursued in joint venture with the Mitsui Group.

The FLNG vessel's operations are targeted for mid-2014.

FLEX LNG has informed InterOil, said the company announcement, that it completed the generic frontend engineering and design (FEED) in 2009. The project-specific FEED is to start in May of this year, working towards an FID before yearend.

The agreements, said the company, represent a continuation of the more than 12-month collaboration among Samsung Heavy Industries, FLEX LNG, InterOil, Pacific LNG, and Liquid Niugini Gas Ltd. (LNGL), InterOil's joint-venture LNG project company with Pacific LNG, to develop the first floating LNG production.

FLEX LNG and Samsung Heavy Industries will be responsible for design, engineering, construction, and commissioning of the FLNG vessel. FLEX LNG will also be joint operator of the FLNG vessel together with LNGL. Construction of the FLNG unit will be fully financed by FLEX LNG and Samsung Heavy Industries.

The FLNG vessel is to be moored alongside the proposed jetty in the Gulf Province, which will be shared with InterOil's proposed land-based LNG facilities, and have production capacity of up to 2 million tpy of LNG and be able to process an estimated 2.25 tcf of gas over 25 years.

FLEX LNG will receive 14.5% of the revenue, less agreed deductions and premiums, from the sale of LNG from the FLNG vessel for an initial 15 years. For the next 5 years, FLEX LNG will receive 12.5% of the revenue and 10% of the revenue for the last 5 years. During the 25 years of the contract, LNGL will become a part owner of the FLNG vessel.

Related Articles

Inpex starts development drilling at Ichthys field

02/04/2015

Inpex Corp. has started development drilling in Ichthys gas-condensate field in the Browse basin, about 200 km offshore Western Australia.

BG’s 2015 budget ‘significantly lower than 2014’

02/03/2015 BG Group plans capital expenditures on a cash basis of $6-7 billion in 2015, a range it says is “significantly lower than 2014” due to “a lower oil...

Live Oak LNG to build Calcasieu Ship Channel liquefaction, export site

02/03/2015 Live Oak LNG LLC, a subsidiary of Parallax Energy LLC, Houston, will invest $2 billion to develop a 5-million tonne/year liquefaction plant and LNG...

Woodside gets NEB approval for British Columbia LNG exports

02/02/2015 Woodside Energy Holdings Pty. Ltd. has received approval from Canada’s National Energy Board on its application for a 25-year natural gas export li...

E&Y: Oil-price collapse to boost global M&A activity in 2015

02/02/2015 The oil-price collapse will facilitate increased global transaction activity in 2015 as companies revise and implement new strategies, according to...

Shell cancels Arrow LNG project

01/30/2015

Royal Dutch Shell PLC has abandoned its plans for what would have been a fourth coal seam gas-LNG project at Gladstone in Queensland.

DOE could meet 45-day LNG export decision deadline, Senate panel told

01/29/2015 The US Department of Energy would have no trouble meeting a 45-day deadline to reach a national interest determination for proposed LNG export faci...

Douglas Channel LNG moves toward 2018 startup

01/29/2015 Exmar NV, EDF Trading, and AIJVLP, a joint venture of AltaGas Ltd. and Idemitsu Kosan Co. Ltd., have taken full ownership of the 550,000 tonne/year...

Mitsui charters two more LNG ships for Cameron export project

01/29/2015 Mitsui & Co., Ltd., Tokyo, reports contracts for chartering two new ships to transport LNG to Japan from the Cameron LNG export project in Loui...
White Papers

Pipeline Integrity: Best Practices to Prevent, Detect, and Mitigate Commodity Releases

Commodity releases can have catastrophic consequences, so ensuring pipeline integrity is crucial for p...
Sponsored by

AVEVA’s Digital Asset Approach - Defining a new era of collaboration in capital projects and asset operations

There is constant, intensive change in the capital projects and asset life cycle management. New chall...
Sponsored by

Transforming the Oil and Gas Industry with EPPM

With budgets in the billions, timelines spanning years, and life cycles extending over decades, oil an...
Sponsored by

Asset Decommissioning in Oil & Gas: Transforming Business

Asset intensive organizations like Oil and Gas have their own industry specific challenges when it com...
Sponsored by

Squeezing the Green: How to Cut Petroleum Downstream Costs and Optimize Processing Efficiencies with Enterprise Project Portfolio Management Solutions

As the downstream petroleum industry grapples with change in every sector and at every level, includin...
Sponsored by

7 Steps to Improve Oil & Gas Asset Decommissioning

Global competition and volatile markets are creating a challenging business climate for project based ...
Sponsored by

The impact of aging infrastructure in process manufacturing industries

Process manufacturing companies in the oil and gas, utilities, chemicals and natural resource industri...
Sponsored by

What is System Level Thermo-Fluid Analysis?

This paper will explain some of the fundamentals of System Level Thermo-Fluid Analysis and demonstrate...
Available Webcasts


The Alternative Fuel Movement: Four Need-to-Know Excise Tax Complexities

When Thu, Jun 4, 2015

Discussion on how to approach, and ultimately embrace, the alternative fuel market by pulling back the veil on excise tax complexities. Taxes may be an aggravating part of daily operations, but their accuracy is crucial in your path towards business success.

register:WEBCAST



On Demand

Prevention, Detection and Mitigation of pipeline leaks in the modern world

Thu, Apr 30, 2015

Preventing, detecting and mitigating leaks or commodity releases from pipelines are a top priority for all pipeline companies. This presentation will look at various aspects related to preventing, detecting and mitigating pipeline commodity releases from a generic and conceptual point of view, while at the same time look at the variety of offerings available from Schneider Electric to meet some of the requirements associated with pipeline integrity management. 

register:WEBCAST


Global LNG: Adjusting to New Realities

Fri, Mar 20, 2015

Oil & Gas Journal’s March 20, 2015, webcast will look at how global LNG trade will be affected over the next 12-24 months by falling crude oil prices and changing patterns and pressures of demand. Will US LNG production play a role in balancing markets? Or will it add to a growing global oversupply of LNG for markets remote from easier natural gas supply? Will new buyers with marginal credit, smaller requirements, or great need for flexibility begin to look attractive to suppliers? How will high-cost, mega-projects in Australia respond to new construction cost trends?

register:WEBCAST


US Midstream at a Crossroads

Fri, Mar 6, 2015

Oil & Gas Journal’s Mar. 6, 2015, webcast will focus on US midstream companies at an inflection point in their development in response to more than 6 years shale oil and gas production growth. Major infrastructure—gas plants, gathering systems, and takeaway pipelines—have been built. Major fractionation hubs have expanded. Given the radically changed pricing environment since mid-2014, where do processors go from here? What is the fate of large projects caught in mid-development? How to producers and processors cooperate to ensure a sustainable and profitable future? This event will serve to set the discussion table for the annual GPA Convention in San Antonio, Apr. 13-16, 2015.

This event is sponsored by Leidos Engineering.

register:WEBCAST


Emerson Micro Motion Videos

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected