HOUSTON, Aug. 12
-- “Production volumes from our commercial operations at Christina Lake, which commenced in August 2009, have safely ramped-up more rapidly than any other SAGD [steam-assisted gravity drainage] project that we are aware of, and with one of the lowest SOR [steam-oil ratio],” said Bill McCaffrey, MEG Energy Corp.'s chairman, president, and chief executive officer in a recent company press release.

MEG's Christina Lake project is in the southern Athabasca area of northeast Alberta and next to Cenovus Energy Inc.'s operated Christina Lake project.

MEG said its second-quarter Christina Lake bitumen production average 24,412 b/d and 26,412 b/d in June with the SOR, a key measure of SAGD efficiency, declining to 2.4 in May and June.

MEG's Christina Lake 3,000 b/d pilot Phase 1 facility started production in 2008 and was integrated with the company's 22,000 b/d Phase 2 facility that started production in August 2009.

In June, the 26,412 b/d production from 29 horizontal well pairs exceeded the 25,000 b/d design capacity of the combined facilities and its 2.4 SOR in June is one of the lowest SORs in Alberta's in situ oil sands industry, MEG said.

Currently MEG has started to circulate steam in two additional horizontal well pairs and it plans to start production from them in the third quarter.

Production during the ramp up averaged 2,493 b/d in third-quarter 2009, 5,920 b/d in fourth-quarter 2009, 13,447 b/d in first-quarter 2010, and 24,562 b/d in second-quarter 2010.

The company expects production to stabilize at 24,000-27,000 b/d.

MEG also plans to start field construction and drilling of horizontal well pairs toward yearend or in 2011 for the 35,000 b/d Christina Lake Phase 2b. It expects to start steaming the wells in 2013.

MEG also has filed in 2008 an application for Christina Lake Phase 3 that would add 150,000 b/d of production. MEG received a completeness decision in May from Alberta Environment in respect of its Phase 3 environmental impact assessment application and in June made a formal request to the Energy Resources Conservation Board for a decision regarding the project application. MEG expects to receive ERCB approvals in late 2010 or 2011.

Related Articles

Cenovus gets AER approval for Grand Rapids oil sands project

03/21/2014 Cenovus Energy Inc. reported that it has received approval from the Alberta Energy Regulator (AER) for its wholly owned Grand Rapids thermal oil sa...

Ivanhoe halts Tamarack oil sands project citing lack of regulatory ‘clarity’

03/18/2014 Ivanhoe Energy Inc. has suspended activity on its Tamarack oil sands project pending approval for its thermal oil sands application from the govern...

CAPP: Emissions monitoring Continues in Alberta oil sands

03/10/2014 Alberta's oil sands producers have monitored emissions for potential public health impacts with the province's government for a while, the Canadian...

Keystone XL national interest comments deadline approaches

03/06/2014 Groups on both sides said support has grown for their positions as the US Department of State’s Mar. 7 deadline approached for comments on whether ...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected