PHMSA orders Enbridge to address problems before restarting pipeline

Nick Snow
OGJ Washington Editor

WASHINGTON, DC, July 30 -- The US Pipeline and Hazardous Materials Safety Administration ordered Enbridge Energy Partners Ltd. on July 28 to immediately correct deficiencies in its Line 6B crude oil pipeline, which sprung a leak 2 days earlier.

The order from PHMSA’s Pipeline Safety Office said the rupture’s cause is still unknown and investigations are continuing. It also said resuming operations of the 30-in. line, which Enbridge shut down soon after its employees discovered the leak, without corrective actions would threaten property, public health, and the environment (OGJ Online, July 29, 2010).

Jeffrey D. Wiese, PHMSA’s associate administrator for pipeline safety, also cited the pipeline’s age; circumstances surrounding its failure; the line’s proximity to populated areas, public roadways, and high-consequence areas; the hazardous nature of the product the pipeline transports; the uncertainties as to the cause of the failure, and the ongoing investigation to determine the cause as reasons for issuing the order without holding a hearing first.

He said the US Department of Transportation agency’s pipeline safety office found in a preliminary inquiry that the affected segment of pipe, which the National Transportation Safety Board will transport to a metallurgist for examination and failure analysis once it has been excavated, was manufactured by Siderius in 1969. The segment has a ¼-in. thick wall and is grade X-52 submerged arc weld pipe. It has a Polyken tape coating and an impressed cathodic protection system.

PHMSA investigators found that the estimated operating pressure at the site when the pipe began to leak was 425 lb-force psig. The line segment’s maximum operating pressure was 624 psig and the MOP at its Marshall Station discharge set point was 523.

Corrosion reassessments
The pipeline, which originates in Griffith, Ind., and extends east to Sarnia, Ont., was last reassessed for corrosion in June 2009 with ultrasonic technology and, prior to that, in October 2007, with magnetic flux leakage technology, according to the order. It said that Enbridge notified PHMSA on July 15 of an alternative remediation plan for metal loss anomalies found in this survey to consider pipe replacement instead of repair. Using this alternative remediation method would take more time, the pipeline’s owner and operator indicated.

PHMSA’s order said that Enbridge will have to develop and submit a written plan to the agency’s central region director in Kansas City, Mo., before restarting the pipeline. It said that the plan will need to provide for the segment to be adequately patrolled as operations resume, including exposure of the line for 50 ft to examine for corrosion, coating condition, or other issues on either side of the replaced segment.

The incremental startup will need to occur during daylight hours after local emergency response officials have been provided details, PHMSA said. It will have to involve 25% pressure increments, each of which will need to be held for at least 1 hour with sufficient surveillance to assure that no leaks are present. Written approval from PHMSA’s regional director will required before operation resumes.

Once the pipeline is restarted, the order continued, Enbridge will need to maintain a 20% reduction in the line’s operating until the agency’s regional director approves a return to full pressure. It also told Enbridge to submit an integrity verification and remedial work plan to the regional director within 60 days, including results of the failed segment’s metallurgical analysis, a failure history of the line’s entire US portion for the last 20 years, a detailed description of inspection and repair criteria for any anomalies that are excavated, and provisions for continuing long-term periodic testing and integrity verification measures.

PHMSA’s order came a day after Michigan Gov. Jennifer M. Granholm (D) declared a state of disaster in potentially affected areas along the Kalamazoo River below Talmadge Creek from the pipeline leak. The declaration reinforces the state’s efforts to protect residents and the environment by making necessary resources readily available, she said on July 27. It also will let the state’s emergency operations center, which she activated with the order, coordinate local, state, federal, and private sector response efforts.

Contact Nick Snow at nicks@pennwell.com.

Related Articles

PHMSA proposes pipeline accident notification regulations

07/02/2015 The US Pipeline and Hazardous Materials Safety Administration has proposed new federal oil and gas pipeline accident and notification regulations. ...

Quicksilver Canada gets LNG export approval

07/02/2015 Quicksilver Resources Canada Inc. has received approval from the National Energy Board of Canada to export 20 million tonnes/year of LNG from a pos...

Origin lets contract for Otway basin fields

07/02/2015 Origin Energy Ltd., Sydney, has let a $1.3 million (Aus.) contract to Wood Group Kenny for provision of a detailed engineering design for the onsho...

API to issue recommended practice to address pipeline safety

07/01/2015 The American Petroleum Institute expects to issue a new recommended practice in another few weeks that addresses pipeline safety issues, but the tr...

Shell Midstream Partners takes interest in Poseidon oil pipeline

07/01/2015 Shell Midstream Partners LP has completed its acquisition of 36% equity interest in Poseidon Oil Pipeline Co. LLC from Equilon Enterprises LLC, a s...

Shell makes FID on Appomattox deepwater development in Gulf of Mexico

07/01/2015 Royal Dutch Shell PLC has taken a final investment decision (FID) on the Appomattox deepwater development, authorizing construction and installatio...

Woodside-led Browse FLNG venture enters FEED phase

07/01/2015 The Woodside Petroleum Ltd.-led Browse LNG joint venture has entered the front-end engineering and design phase for a floating LNG (FLNG) developme...

Case for Keystone XL has grown stronger, TransCanada tells Kerry

06/30/2015 Canada is taking strong steps toward combating climate change, and the proposed Keystone XL pipeline crude oil pipeline remains in the US national ...

Construction begins on Chinese section of Russia-China Gas Pipeline

06/30/2015

Construction has begun on the Chinese section of the Russia-China Gas Pipeline, according to China National Petroleum Corp.

White Papers

2015 Global Engineering Information Management Solutions Competitive Strategy Innovation and Leadership Award

The Frost & Sullivan Best Practices Awards recognise companies in a variety of regional and global...
Sponsored by

Three Tips to Improve Safety in the Oil Field

Working oil fields will always be tough work with inherent risks. There’s no getting around that. Ther...
Sponsored by

Pipeline Integrity: Best Practices to Prevent, Detect, and Mitigate Commodity Releases

Commodity releases can have catastrophic consequences, so ensuring pipeline integrity is crucial for p...
Sponsored by

AVEVA’s Digital Asset Approach - Defining a new era of collaboration in capital projects and asset operations

There is constant, intensive change in the capital projects and asset life cycle management. New chall...
Sponsored by

Transforming the Oil and Gas Industry with EPPM

With budgets in the billions, timelines spanning years, and life cycles extending over decades, oil an...
Sponsored by

Asset Decommissioning in Oil & Gas: Transforming Business

Asset intensive organizations like Oil and Gas have their own industry specific challenges when it com...
Sponsored by

Squeezing the Green: How to Cut Petroleum Downstream Costs and Optimize Processing Efficiencies with Enterprise Project Portfolio Management Solutions

As the downstream petroleum industry grapples with change in every sector and at every level, includin...
Sponsored by

7 Steps to Improve Oil & Gas Asset Decommissioning

Global competition and volatile markets are creating a challenging business climate for project based ...
Sponsored by
Available Webcasts


OGJ's Midyear Forecast 2015

When Fri, Jul 10, 2015

This webcast is to be presented by OGJ Editor Bob Tippee and Senior Economic Editor Conglin Xu.  They will summarize the Midyear Forecast projections in key categories, note important changes from January’s forecasts, and examine reasons for the adjustments.

register:WEBCAST


Predictive Analytics in your digital oilfield - Optimize Production Yield and Reduce Operational Costs

When Tue, Jul 7, 2015

Putting predictive analytics to work in your oilfield can help you anticipate failures, plan and schedule work in advance, eliminate emergency work and catastrophic failures, and at the same time you can optimize working capital and improve resource utilization.  When you apply analytic capabilities to critical production assets it is possible to reduce non-productive time and increase your yield.

Learn how IBM's analytics capabilities can be applied to critical production assets with the goal of reducing non-productive time, increasing yield and reducing operations costs.

register:WEBCAST



On Demand

Cognitive Solutions for Upstream Oil and Gas

Fri, Jun 12, 2015

The oil & gas sector is under pressure on all sides. Reserves are limited and it’s becoming increasingly expensive to find and extract new resources. Margins are already being squeezed in an industry where one wrong decision can cost millions. Analyzing data used in energy exploration can save millions of dollars as we develop ways to predict where and how to extract the world’s massive energy reserves.

This session with IBM Subject Matter Experts will discuss how IBM Cognitive Solutions contribute to the oil and gas industry using predictive analytics and cognitive computing, as well as real time streaming for exploration and drilling.

register:WEBCAST


The Alternative Fuel Movement: Four Need-to-Know Excise Tax Complexities

Thu, Jun 4, 2015

Discussion on how to approach, and ultimately embrace, the alternative fuel market by pulling back the veil on excise tax complexities. Taxes may be an aggravating part of daily operations, but their accuracy is crucial in your path towards business success.

register:WEBCAST


Emerson Micro Motion Videos

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected