BP reports progress with sealing cap installation

Paula Dittrick
OGJ Senior Staff Writer

HOUSTON, July 12 --
BP PLC, operator of the runaway Macondo well, removed the lower marine riser package (LMRP) containment cap over the Deepwater Horizon’s failed blowout preventer and was installing a sealing cap assembly on June 12.

The sealing cap installation involves multiple stages, and BP estimates the process, which started on July 10, could take 4-7 days. The sealing cap is intended to increase oil and gas collection capacity. It’s expected to improve collection efficiency during hurricane season by allowing shorter disconnect and reconnect times,.

The sealing cap assembly also could help well kill and cementing procedures that will be part of the relief well operations. In addition, the sealing cap will enable testing of well integrity and, depending on pressure measurements, might be used to shut in the well.

The Helix Producer collection system was expected to begin operations within the next 24 hr (OGJ Online, July 9, 2010). The producer is a floating production unit, with a floating riser collection system. Once installed and the system is gradually ramped up, the Producer will collect an anticipated 20,000-25,000 b/d.

During July 10-11, BP fixed problems with a hydraulic system that operates a valve and then had to fix a leak in a methanol system.

An Apr. 20 blowout of the Macondo well caused a fire and explosion on Transocean Ltd.’s Deepwater Horizon semisubmersible, killing 11 workers. On Apr. 22, the rig sank, and oil spill response crews have been working to stop an ongoing spill.

LMRP cap removed
Transocean’s Discoverer Enterprise drillship removed the LMRP cap at 12:40 p.m. CDT on July 10. Crews using remotely operated vehicles removed six bolts along with a flange from the LMRP. A transition spool was installed on an existing flange.

The transition spool is a connector allowing installation of a capping stack that has three closing rams. After the capping stack is installed, BP plans a well integrity test in which it plans to stop the flow of oil and gas from the top of the Macondo well while pressure within the well is measured.

The Helix Q4000 collection system continues to capture oil and gas from the MC252 well and flare the hydrocarbons at the surface. Plans also are being developed for additional containment capacity to increase capacity to 60,000-80,000 b/d by July 31.

Relief wells getting closer
Work on the first relief well, which started May 2, continues. The well being drilled by the Development Driller III reached a measured depth of 17,810 ft on July 11 and 10 ranging runs have been completed to precisely locate the Macondo well.

Following the running of casing and additional ranging runs, the relief well is intended to intercept the Macondo well at about 18,000 ft. Crews then will start the process of killing the flow of oil and gas from the reservoir by pumping specialized heavy fluids down the relief well.

A second relief well, which started May 16, has reached a measured depth of 15,874 ft, and crews prepared to set casing. After that, drilling on the second relief well will be stopped unless crews run into problems with the first relief well, said Kent Wells, BP senior vice-president of exploration and production.

The first half of August remains the current estimate of the most likely date by which the first relief well will be completed, he said. 

Contact Paula Dittrick at paulad@ogjonline.com.

Related Articles

County decision in Washington state stalls Shell’s Bakken rail plans

02/24/2015 A Skagit County Hearing Examiner in Mount Vernon, Wash., halted Royal Dutch Shell PLC’s plans to move Bakken crude oil by rail to the company’s Ana...

Work stoppages commence at largest US refinery, three other facilities

02/23/2015 The United Steelworkers union (USW) has launched additional work stoppages at the largest refinery in the US and three other facilities as part of ...

AER sets new seismic monitoring rules for Duvernay in the Fox Creek area

02/23/2015 The Alberta Energy Regulator (AER) announced seismic monitoring and reporting requirements for companies using hydraulic fracturing in the Duvernay...

Montana governor wants PHMSA to beef up pipeline enforcement in state

02/23/2015 Citing a Jan. 17 leak of 1,200 bbl of crude oil from a ruptured pipeline in eastern Montana, Gov. Steve Bullock (D) asked US Sec. of Transportation...

US House vote sends Keystone XL approval bill to Obama's desk

02/23/2015 The US House of Representatives voted by 270 to 152 to pass S. 1, which would deem the proposed Keystone XL crude oil pipeline approved more than 6...

DOI proposes Arctic-specific drilling regulations for Alaska OCS

02/20/2015 The US Department of the Interior proposed regulations to ensure that oil and gas exploration on the US Arctic Continental Shelf occur safely and r...

ExxonMobil investigating explosion at Torrance refinery

02/19/2015 An investigation is under way into the cause of an explosion and ensuing fire that took place at ExxonMobil Corp.’s 149,500-b/d Torrance, Calif., r...

Comments sought on Pinedale Anticline gas field noise report

02/18/2015 The US Bureau of Land Management’s Pinedale Anticline Project Office (PAPO) is seeking public comments on a 2014 acoustic noise report on sound lev...

Another cut seen in Groningen gas output

02/18/2015 Production from giant Groningen natural gas field in the Netherlands might be further curtailed in response to public concern about earthquakes.
White Papers

Pipeline Integrity: Best Practices to Prevent, Detect, and Mitigate Commodity Releases

Commodity releases can have catastrophic consequences, so ensuring pipeline integrity is crucial for p...
Sponsored by

AVEVA’s Digital Asset Approach - Defining a new era of collaboration in capital projects and asset operations

There is constant, intensive change in the capital projects and asset life cycle management. New chall...
Sponsored by

Transforming the Oil and Gas Industry with EPPM

With budgets in the billions, timelines spanning years, and life cycles extending over decades, oil an...
Sponsored by

Asset Decommissioning in Oil & Gas: Transforming Business

Asset intensive organizations like Oil and Gas have their own industry specific challenges when it com...
Sponsored by

Squeezing the Green: How to Cut Petroleum Downstream Costs and Optimize Processing Efficiencies with Enterprise Project Portfolio Management Solutions

As the downstream petroleum industry grapples with change in every sector and at every level, includin...
Sponsored by

7 Steps to Improve Oil & Gas Asset Decommissioning

Global competition and volatile markets are creating a challenging business climate for project based ...
Sponsored by

The impact of aging infrastructure in process manufacturing industries

Process manufacturing companies in the oil and gas, utilities, chemicals and natural resource industri...
Sponsored by

What is System Level Thermo-Fluid Analysis?

This paper will explain some of the fundamentals of System Level Thermo-Fluid Analysis and demonstrate...
Available Webcasts


Prevention, Detection and Mitigation of pipeline leaks in the modern world

When Thu, Apr 30, 2015

Preventing, detecting and mitigating leaks or commodity releases from pipelines are a top priority for all pipeline companies. This presentation will look at various aspects related to preventing, detecting and mitigating pipeline commodity releases from a generic and conceptual point of view, while at the same time look at the variety of offerings available from Schneider Electric to meet some of the requirements associated with pipeline integrity management. 

register:WEBCAST



On Demand

Global LNG: Adjusting to New Realities

Fri, Mar 20, 2015

Oil & Gas Journal’s March 20, 2015, webcast will look at how global LNG trade will be affected over the next 12-24 months by falling crude oil prices and changing patterns and pressures of demand. Will US LNG production play a role in balancing markets? Or will it add to a growing global oversupply of LNG for markets remote from easier natural gas supply? Will new buyers with marginal credit, smaller requirements, or great need for flexibility begin to look attractive to suppliers? How will high-cost, mega-projects in Australia respond to new construction cost trends?

register:WEBCAST


US Midstream at a Crossroads

Fri, Mar 6, 2015

Oil & Gas Journal’s Mar. 6, 2015, webcast will focus on US midstream companies at an inflection point in their development in response to more than 6 years shale oil and gas production growth. Major infrastructure—gas plants, gathering systems, and takeaway pipelines—have been built. Major fractionation hubs have expanded. Given the radically changed pricing environment since mid-2014, where do processors go from here? What is the fate of large projects caught in mid-development? How to producers and processors cooperate to ensure a sustainable and profitable future? This event will serve to set the discussion table for the annual GPA Convention in San Antonio, Apr. 13-16, 2015.

This event is sponsored by Leidos Engineering.

register:WEBCAST


The Future of US Refining

Fri, Feb 6, 2015

Oil & Gas Journal’s Feb. 6, 2015, webcast will focus on the future of US refining as various forces this year conspire to pull the industry in different directions. Lower oil prices generally reduce feedstock costs, but they have also lowered refiners’ returns, as 2015 begins with refined products priced at lows not seen in years. If lower per-barrel crude prices dampen production of lighter crudes among shale plays, what will happen to refiners’ plans to export more barrels of lighter crudes? And as always, refiners will be affected by government regulations, particularly those that suppress demand, increase costs, or limit access to markets or supply.

register:WEBCAST


Emerson Micro Motion Videos

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected