BP to install different cap along with floating risers in gulf

Paula Dittrick
OGJ Senior Staff Writer

HOUSTON, June 17 -- A different containment cap will be included as part of BP PLC’s efforts to install more hurricane-durable systems for collecting oil from the runaway Macondo well in the deepwater Gulf of Mexico.

National Incident Commander and retired US Coast Guard Adm. Thad Allen said plans call for the Discoverer Enterprise drillship and the Q4000 multiservice vessel eventually to be disconnected from the well so that a new containment cap can be put into place.

The existing lower marine riser package (LMRP) cap allows some leakage. Allen said an “absolute cap that would allow no oil to escape” will be installed, enabling greater collection capacity.

The new cap is expected to be installed while the collection delivery system is switched from fixed risers to floating risers. Equipment and vessels are coming from Brazil and the North Sea to set up the floating riser systems, Allen said.

Floating risers will enable surface vessels to disconnect from the system if needed in case a hurricane hits the gulf. The spill response will be the first time that floating risers have been used in the gulf, Allen said.

“We think this is low-risk, but it takes a long time to get the equipment,” he said.

Q4000 collecting, burning oil
The LMRP cap is connected to a fixed riser that connects with the Enterprise on the surface. The Q4000 direct connect involves a seafloor manifold that is connected to the failed Deepwater Horizon BOP. Earlier this week, the Q4000 started receiving oil in addition to volumes being collected on the Enterprise (OGJ Online, June 16, 2010).

BP will have the capacity to capture about 28,000 b/d “sometime early next week,” Allen said during a June 17 conference call. The Q4000 uses a specialized clean-burning system to flare both oil and gas. On the Enterprise, gas is flared and the oil is moved to a lightering vessel for delivery to Mobile, Ala.

By June 30 BP hopes to have installed containment enhancements to provide a collection capacity of 40,000-53,000 b/d. By mid-July, BP hopes to have a system with a collection capacity of 60,000-80,000 b/d.

The containment systems are temporary measures until completion of at least one of two relief wells being drilled. The anticipated relief well completion date is sometime in August.

The Development Driller III, which is drilling the first relief well, has reached a depth of more than 15,000 ft and is 11 days ahead of schedule, Allen said.

According to a June 16 news release from the Deepwater Horizon Incident Joint Information Center, the relief well being drilled by Development Driller III is beginning to angle at 23º. Meanwhile, the Development Driller II has drilled the second relief well to a depth of 9,774 ft. The Macondo well was drilled to 18,000 ft.

Contact Paula Dittrick at paulad@ogjonline.com.

Related Articles

BP trims capital budget by $4-6 billion

02/03/2015 BP PLC plans an organic capital expenditure of $20 billion in 2015, down from the previous guidance $24-26 billion. Total organic capital expenditu...

EPA suggests DOS reconsider Keystone XL climate impact conclusions

02/03/2015 The US Department of State might want to reconsider its conclusions regarding potential climate impacts from the proposed Keystone XL crude oil pip...

Kerry expects to receive other agencies’ Keystone XL reports soon

02/02/2015 US Sec. of State John F. Kerry said he expects to receive other federal agencies and departments’ reports soon on the proposed Keystone XL crude oi...

Union strike under way at US refineries, petchem plants

02/02/2015 The United Steelworkers Union (USW) has instituted a strike at nine US refining and petrochemical production plants following a breakdown in negoti...

Victoria extends drilling, fracing ban

01/30/2015 The new Victorian Labor government of premier Daniel Andrews has extended the coal seam gas (CSG) exploration and hydraulic fracturing ban in the s...

US Senate passes bill approving Keystone XL pipeline project

01/30/2015 The US Senate has passed a bill approving construction of the proposed Keystone XL crude oil pipeline by a 62-36 vote after 3 weeks of debate. Nine...

Pennsylvania governor reinstates state forest drilling moratorium

01/29/2015 Pennsylvania Gov. Tom Wolf (D) signed an executive order fully reinstating a 2010 moratorium on new oil and gas leases in state forests and parks. ...

DOE could meet 45-day LNG export decision deadline, Senate panel told

01/29/2015 The US Department of Energy would have no trouble meeting a 45-day deadline to reach a national interest determination for proposed LNG export faci...

PHMSA outlines community steps to reduce pipeline incident risks

01/27/2015 The US Pipeline and Hazardous Materials Safety Administration released a guide to best practices for communities to reduce risks from pipeline inci...
White Papers

Three Tips to Improve Safety in the Oil Field

Working oil fields will always be tough work with inherent risks. There’s no getting around that. Ther...
Sponsored by

Pipeline Integrity: Best Practices to Prevent, Detect, and Mitigate Commodity Releases

Commodity releases can have catastrophic consequences, so ensuring pipeline integrity is crucial for p...
Sponsored by

AVEVA’s Digital Asset Approach - Defining a new era of collaboration in capital projects and asset operations

There is constant, intensive change in the capital projects and asset life cycle management. New chall...
Sponsored by

Transforming the Oil and Gas Industry with EPPM

With budgets in the billions, timelines spanning years, and life cycles extending over decades, oil an...
Sponsored by

Asset Decommissioning in Oil & Gas: Transforming Business

Asset intensive organizations like Oil and Gas have their own industry specific challenges when it com...
Sponsored by

Squeezing the Green: How to Cut Petroleum Downstream Costs and Optimize Processing Efficiencies with Enterprise Project Portfolio Management Solutions

As the downstream petroleum industry grapples with change in every sector and at every level, includin...
Sponsored by

7 Steps to Improve Oil & Gas Asset Decommissioning

Global competition and volatile markets are creating a challenging business climate for project based ...
Sponsored by

The impact of aging infrastructure in process manufacturing industries

Process manufacturing companies in the oil and gas, utilities, chemicals and natural resource industri...
Sponsored by
Available Webcasts


OGJ's Midyear Forecast 2015

When Fri, Jul 10, 2015

This webcast is to be presented by OGJ Editor Bob Tippee and Senior Economic Editor Conglin Xu.  They will summarize the Midyear Forecast projections in key categories, note important changes from January’s forecasts, and examine reasons for the adjustments.

register:WEBCAST


Predictive Analytics in your digital oilfield - Optimize Production Yield and Reduce Operational Costs

When Tue, Jul 7, 2015

Putting predictive analytics to work in your oilfield can help you anticipate failures, plan and schedule work in advance, eliminate emergency work and catastrophic failures, and at the same time you can optimize working capital and improve resource utilization.  When you apply analytic capabilities to critical production assets it is possible to reduce non-productive time and increase your yield.

Learn how IBM's analytics capabilities can be applied to critical production assets with the goal of reducing non-productive time, increasing yield and reducing operations costs.

register:WEBCAST



On Demand

Cognitive Solutions for Upstream Oil and Gas

Fri, Jun 12, 2015

The oil & gas sector is under pressure on all sides. Reserves are limited and it’s becoming increasingly expensive to find and extract new resources. Margins are already being squeezed in an industry where one wrong decision can cost millions. Analyzing data used in energy exploration can save millions of dollars as we develop ways to predict where and how to extract the world’s massive energy reserves.

This session with IBM Subject Matter Experts will discuss how IBM Cognitive Solutions contribute to the oil and gas industry using predictive analytics and cognitive computing, as well as real time streaming for exploration and drilling.

register:WEBCAST


The Alternative Fuel Movement: Four Need-to-Know Excise Tax Complexities

Thu, Jun 4, 2015

Discussion on how to approach, and ultimately embrace, the alternative fuel market by pulling back the veil on excise tax complexities. Taxes may be an aggravating part of daily operations, but their accuracy is crucial in your path towards business success.

register:WEBCAST


Emerson Micro Motion Videos

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected