BP reports delays in cutting off Deepwater Horizon riser

(June 3 update: the saw was freed and cut was made with shears)

Paula Dittrick
OGJ Senior Staff Writer

HOUSTON, June 2 -- BP PLC successfully made the first of two cuts in the damaged Deepwater Horizon riser on the seabed, but while making the second cut, crews reported the diamond-wire saw was binding as it moved horizontally through the riser, said National Incident Commander and Adm. Thad Allen.

“The cleaner the cut, the tighter the seal we can make,” Allen said, adding that the goal is to finish making the horizontal cut on June 2 so that a cap can be placed on top of the failed blowout preventer’s lower marine riser package (LMRP) to enable the collection of oil and gas flowing from the runaway Macondo well. Collected oil and gas will go to a drillship.

Crews were trying to reposition the riser so the saw could move again, he said, adding it was possible that the saw might have to be brought to the surface to resolve the problem.

In other news, Allen confirmed that oil had reached Petit Bois Island, a barrier island in the Mississippi Sound near the Mississippi-Alabama border. Oil previously reached shore in Louisiana and Alabama. There are some reports of oil on Pensacola beach in Florida, but Allen said officials have yet to confirm those reports.

An Apr. 20 fire and explosion on Transocean Ltd.’s Deepwater Horizon semisubmersible, which was drilling for BP and its partners, left 11 crew members dead. The Deepwater Horizon sank Apr. 22. Following a May 29 announcement that the “top kill” operation had failed to stem the flow from the leaking well, crews moved to deploy a LMRP cap containment system.

Various caps are sitting on the seabed in 5,000 ft of water, and the one that will be used is dependent upon the flatness and smoothness of the cut across the failed BOP’s LMRP, BP executives have said (OGJ Online, June 1, 2010).

Contact Paula Dittrick at paulad@ogjonline.com.

Related Articles

Judge bars Anadarko e-mails as evidence in Macondo blowout hearing

03/21/2014 A federal district judge in New Orleans refused to accept e-mails between Anadarko Petroleum Corp. and BP PLC as evidence in a hearing to determine...

BOEM extends proposed higher offshore liability limit comment period

03/20/2014 The US Bureau of Ocean Energy Management added 30 days to the public comment period for its proposed higher liability limit for offshore oil and ga...

Begich objects to House Democrats’ NPR-A comment extension request

03/18/2014 US Sen. Mark Begich (D-Alas.) let three US House Democrats know he did not approve of their request for the US Bureau of Land Management to add 30 ...

EPA lifts post-Macondo contract suspension in agreement with BP

03/14/2014 The US Environmental Protection Agency and BP PLC reached an agreement that will effectively end the bar on new federal contracts imposed on the mu...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected