Chevron awards another Big Foot contract

By OGJ editors
HOUSTON, Dec. 4
-- Chevron USA Inc. let a contract to FloaTEC LLC for front-end engineering and design of the hull, mooring, and risers for the Big Foot dry-tree floating drilling and production facility in 5,300 ft of water in the Gulf of Mexico.

Chevron earlier let a FEED contract to KBR Inc. for topsides (OGJ Online, Nov. 2, 2009).

Big Foot oil field is on Walker Ridge Block 29 about 200 miles from New Orleans.

The hull of the proposed facility would be an extended tension-leg platform based on proprietary technology of FloaTEC, a deepwater joint venture of Keppel FELS and J. Ray McDermott.

FloaTEC also will assist with cost estimates and plans for later development phases.

Chevron’s partners in the block are Statoil Gulf of Mexico LLC and Marubeni Oil & Gas (USA) Inc.

Related Articles

Chevron to increase production, maintain capex level through 2017

03/13/2014 Chevron Corp. will increase production by 20% through 2017 without raising capital expenditures, executives said Mar. 11 at the company's annual se...

IHS CERAWeek: Oil executives cite rising business costs

03/04/2014 Demand for all types of energy continues to increase as oil and gas companies adapt to handle the ever-rising costs of finding and producing hydroc...

Chevron gets approval for Alder field, reaches FID

01/20/2014 Chevron Corp. UK subsidiary Chevron North Sea Ltd. has reached a final investment decision (FID) and received approval from the UK government to pr...

Feds call for revamp in safety regulation at US refineries

12/23/2013 The US Chemical Safety Board (CSB) has proposed a more-rigorous safety management regulatory framework for refineries in California that could exte...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected