Gassco to improve blow-down system at LNG terminals

Uchenna Izundu
OGJ International Editor

LONDON, Aug. 5 -- Gassco AS contracted Foster Wheeler Energy Ltd. to modify its blow-down system at its 6.6 million tonnes/year LNG terminal at Zeebrugge, Belgium, and proposed one in Dunkerque, France. The contract value was not disclosed. 

Foster Wheeler is scheduled to finish the engineering, procurement, and construction contract in 2010 for the Zeebrugge LNG terminal. Foster Wheeler will focus on concept development and pre-engineering of the blow-down system at Dunkerque terminal following its successful completion of the study phase.

A blow-down system safely depressurizes the process areas of a gas terminal when there’s an emergency.

The company already reviewed the process in Zeebrugge and suggested various means to reduce the risk of escalation in the inlet and process areas if there was a fire.

“The concept development and pre-engineering work for Dunkerque will involve further development of the proposed solution, identified in the completed study, to optimize the blow-down system to meet venting time recommendations for the fire-affected areas. This work will support Gassco in seeking approval to proceed with project implementation,” said Foster Wheeler.

Dunkerque LNG is scheduled to come on stream in 2014 and is being spearheaded by EDF. The final investment decision will be taken in the first 6 months of next year and it is considered to be a strategic project in diversifying Europe’s energy sources. It will have a capacity of 10-13 billion cu m/year.

Contact Uchenna Izundu at uchennai@pennwell.com.

Related Articles

INGAA Foundation forecasts oil, gas infrastructure outlays to 2035

03/18/2014 An estimated $640.9 billion, or an average $29.1 billion/year, will need to be spent on US and Canadian midstream crude oil, natural gas, and natur...

Cameron LNG awards export-plant contracts

03/17/2014 Cameron LNG LLC has awarded CB&I and Chiyoda International Corp. a $6 billion engineering, procurement, and construction contract to build a 13...

IOC to buy stake in proposed PNW LNG terminal

03/17/2014 Indian Oil Corp. Ltd. (IOC) has signed an agreement with Progress Energy Canada Ltd., Calgary; Pacific Northwest LNG Ltd. (PNW LNG), Vancouver, BC;...

FERC issues draft EIS on Freeport LNG’s Phase II projects

03/14/2014 The US Federal Energy Regulatory Commission has issued a draft environmental impact statement (EIS) on Freeport LNG’s Phase II modification and liq...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected