Regas units for floating LNG being installed

By OGJ editors
HOUSTON, July 22
-- Testing of LNG regasification packages for floating installations is taking place this summer in advance of commissioning off Brazil, Boston, and Dubai. The units are supplied by Hamworthy PLC, Dorset, UK.

Brazil
Work is under way in the Keppel Shipyard, Singapore, to install three Hamworthy LNG propane regasification skids aboard the floating storage and regasification unit (FSRU) Golar Winter, said the supplier in an announcement. Chartered by Petroleo Brasileiro SA (Petrobras), the 138,000-cu m vessel will soon sail for Brazil to tie up in Guanabara Bay, Rio de Janeiro, and send vaporized LNG into the local onshore grid. Gas trials and start-up are to take place this month.

Hamworthy delivered the three skids at the end of 2008. Capacity of each skid is 7 million cu m/day; outlet pressure is 103 bar (about 1,500 psi), and outlet temperature up to 6° C. Two skids will be used during nominal send-out, said the supplier, while the third is on standby.

Each 70-tonne skid is 10.5 m long, 6.1 m wide, 8 m high, and contains pumps, motors, heat exchangers, instrumentation, and control systems. The equipment is designed for marine installations and cryogenic working conditions and can handle large variations in send-out capacity, said the Hamworthy announcement.

“The equipment…is based on seawater heating and therefore requires less fuel and operating cost to regasify the LNG than steam-based systems,” said Tore Lunde, managing director of Hamworthy Gas Systems. The Golar Winter system is based on seawater heating in a closed propane loop; the intermediate propane circuit between seawater and LNG is applied to avoid freezing.

Petrobras completed installation on its first floating regas terminal, at Pecem, Ceara state, earlier this year. That vessel is the 127,000-cu m Golar Spirit (OGJ, Mar. 16, 2009, p. 64).

Off Boston, Dubai
Golar Winter’s plant was the company’s second system to be delivered. Hamworthy delivered the first plant in summer 2008 for installation aboard the 145,000-cu m LNG shuttle regasification vessel (SRV) Suez Neptune. That vessel is the first of two SRVs ordered from Samsung in South Korea for Hoegh LNG to serve the Neptune terminal off Boston. Gas trials are scheduled for next month.

SRVs are designed to transport and store LNG and then vaporize it to be sent ashore by subsea pipeline. Hamworthy is supplying three regasification skids per ship. Each ship’s set will have a regasification capacity of 210 tonnes/hr of LNG with send-out pressure of 115 bar. Gas trials will be taking place on the second Neptune SRV, Suez Cape Ann, in June 2010.

Hamworthy’s third regasification project is for the 126,000-cu m FSRU Golar Freeze for Dubai Supply Authority and Shell in Dubai. Hamworthy is delivering the regasification skids for this vessel in September, it said.

The system will be installed on the 1977-built LNG carrier that is being converted into an FSRU before being time-chartered by Dubai Supply for 10 years, with options to extend for up to another 5 years.

After its delivery to DUSUP in second quarter 2010, Hamworthy says the Golar Freeze will be permanently moored alongside a purpose-built jetty within the existing Jebel Ali port. The FSRU will be capable of storing 125,000 cu m of LNG and delivering up to 14 million cu m/day (about 3 million tonnes/year) of regasified LNG to Dubai Supply for delivery into the Dubai gas network.

Related Articles

Inpex starts development drilling at Ichthys field

02/04/2015

Inpex Corp. has started development drilling in Ichthys gas-condensate field in the Browse basin, about 200 km offshore Western Australia.

BG’s 2015 budget ‘significantly lower than 2014’

02/03/2015 BG Group plans capital expenditures on a cash basis of $6-7 billion in 2015, a range it says is “significantly lower than 2014” due to “a lower oil...

Live Oak LNG to build Calcasieu Ship Channel liquefaction, export site

02/03/2015 Live Oak LNG LLC, a subsidiary of Parallax Energy LLC, Houston, will invest $2 billion to develop a 5-million tonne/year liquefaction plant and LNG...

Woodside gets NEB approval for British Columbia LNG exports

02/02/2015 Woodside Energy Holdings Pty. Ltd. has received approval from Canada’s National Energy Board on its application for a 25-year natural gas export li...

E&Y: Oil-price collapse to boost global M&A activity in 2015

02/02/2015 The oil-price collapse will facilitate increased global transaction activity in 2015 as companies revise and implement new strategies, according to...

Shell cancels Arrow LNG project

01/30/2015

Royal Dutch Shell PLC has abandoned its plans for what would have been a fourth coal seam gas-LNG project at Gladstone in Queensland.

DOE could meet 45-day LNG export decision deadline, Senate panel told

01/29/2015 The US Department of Energy would have no trouble meeting a 45-day deadline to reach a national interest determination for proposed LNG export faci...

Douglas Channel LNG moves toward 2018 startup

01/29/2015 Exmar NV, EDF Trading, and AIJVLP, a joint venture of AltaGas Ltd. and Idemitsu Kosan Co. Ltd., have taken full ownership of the 550,000 tonne/year...

Mitsui charters two more LNG ships for Cameron export project

01/29/2015 Mitsui & Co., Ltd., Tokyo, reports contracts for chartering two new ships to transport LNG to Japan from the Cameron LNG export project in Loui...
White Papers

Three Tips to Improve Safety in the Oil Field

Working oil fields will always be tough work with inherent risks. There’s no getting around that. Ther...
Sponsored by

Pipeline Integrity: Best Practices to Prevent, Detect, and Mitigate Commodity Releases

Commodity releases can have catastrophic consequences, so ensuring pipeline integrity is crucial for p...
Sponsored by

AVEVA’s Digital Asset Approach - Defining a new era of collaboration in capital projects and asset operations

There is constant, intensive change in the capital projects and asset life cycle management. New chall...
Sponsored by

Transforming the Oil and Gas Industry with EPPM

With budgets in the billions, timelines spanning years, and life cycles extending over decades, oil an...
Sponsored by

Asset Decommissioning in Oil & Gas: Transforming Business

Asset intensive organizations like Oil and Gas have their own industry specific challenges when it com...
Sponsored by

Squeezing the Green: How to Cut Petroleum Downstream Costs and Optimize Processing Efficiencies with Enterprise Project Portfolio Management Solutions

As the downstream petroleum industry grapples with change in every sector and at every level, includin...
Sponsored by

7 Steps to Improve Oil & Gas Asset Decommissioning

Global competition and volatile markets are creating a challenging business climate for project based ...
Sponsored by

The impact of aging infrastructure in process manufacturing industries

Process manufacturing companies in the oil and gas, utilities, chemicals and natural resource industri...
Sponsored by
Available Webcasts


OGJ's Midyear Forecast 2015

When Fri, Jul 10, 2015

This webcast is to be presented by OGJ Editor Bob Tippee and Senior Economic Editor Conglin Xu.  They will summarize the Midyear Forecast projections in key categories, note important changes from January’s forecasts, and examine reasons for the adjustments.

register:WEBCAST


Predictive Analytics in your digital oilfield - Optimize Production Yield and Reduce Operational Costs

When Tue, Jul 7, 2015

Putting predictive analytics to work in your oilfield can help you anticipate failures, plan and schedule work in advance, eliminate emergency work and catastrophic failures, and at the same time you can optimize working capital and improve resource utilization.  When you apply analytic capabilities to critical production assets it is possible to reduce non-productive time and increase your yield.

Learn how IBM's analytics capabilities can be applied to critical production assets with the goal of reducing non-productive time, increasing yield and reducing operations costs.

register:WEBCAST



On Demand

Cognitive Solutions for Upstream Oil and Gas

Fri, Jun 12, 2015

The oil & gas sector is under pressure on all sides. Reserves are limited and it’s becoming increasingly expensive to find and extract new resources. Margins are already being squeezed in an industry where one wrong decision can cost millions. Analyzing data used in energy exploration can save millions of dollars as we develop ways to predict where and how to extract the world’s massive energy reserves.

This session with IBM Subject Matter Experts will discuss how IBM Cognitive Solutions contribute to the oil and gas industry using predictive analytics and cognitive computing, as well as real time streaming for exploration and drilling.

register:WEBCAST


The Alternative Fuel Movement: Four Need-to-Know Excise Tax Complexities

Thu, Jun 4, 2015

Discussion on how to approach, and ultimately embrace, the alternative fuel market by pulling back the veil on excise tax complexities. Taxes may be an aggravating part of daily operations, but their accuracy is crucial in your path towards business success.

register:WEBCAST


Emerson Micro Motion Videos

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected