FERC issues final EIS for proposed LNG project near Baltimore

The Federal Energy Regulatory Commission's staff identified additional adverse environmental impacts as it issued a final environmental impact statement on Dec. 5 for a proposed liquefied natural gas project outside Baltimore.

But the staff said that such impacts would be "mostly limited" from the LNG import terminal and associated pipeline. The final EIS's conclusion was similar to one reached in its draft EIS of the project on April 25, which noted that AES Corp. plans to build the terminal within an industrial port setting at Sparrows Point. The facility would be capable of storing up to 480,000 cubic meters of LNG with a baseload send-out rate of 1.5 billion cubic feet per day of revaporized natural gas, FERC said.

Maryland state and local government officials have expressed opposition to the project, saying it would bring LNG tankers up Chesapeake Bay and potentially disrupt Baltimore Harbor vessel traffic. Two members of the state's congressional delegation said on Dec. 5 that they were not satisfied with FERC's final EIS.

US Sen. Barbara A. Mikulski (D-Md.) said on Dec. 5 that the number of recommended mitigation measures grew from 151 in the draft EIS to 179 in the latest document. "I remain firmly opposed to a new LNG facility at Sparrows Point. For over two years, I have repeatedly raised my safety, security and environmental concerns about this LNG facility and pipeline. I am deeply disappointed that FERC continues to rubber stamp a project that our state is adamantly opposed to," she declared.

"This is a tough setback, but I will not give up the fight to stop the proposed LNG facility from coming to eastern Baltimore County. I have said from the very beginning this proposed liquefied natural gas plant is absolutely inappropriate for this residential area," said Rep. C.A. "Dutch" Ruppersberger. The final EIS "ignores the safety of nearby residents who would live in the shadow of the facility," he charged.

More mitigation measures

FERC's staff said in the final EIS that the US Coast Guard's Waterway Suitability Report for the project has "preliminarily determined" that additional recommended mitigation measures would be needed to make the Patapsco River, Chesapeake Bay and territorial seas suitable for LNG marine traffic to the proposed terminal site and responsibly manage marine and safety risks.

"Along the marine transit route, potential impacts, thought short-term, could be significant to boaters and fishermen by interfering with their normal and accustomed practices of using the Chesapeake Bay and Patapsco River," it conceded.

AES would need to coordinate with the Port of Baltimore and with special boating interest groups to minimize disruption of scheduled annual maritime events, the final EIS suggested. "Coordination with the Coast Guard's Marine Event Permit Office would be necessary since events may require LNG vessels to adjust their transit . . . We have also recommended that AES work with the Coast Guard and Patuxent River Naval Air Station during development of its transit management plan," it said.

FERC's final EIS also said that the proposed project's construction would have a temporary impact on about 1,801 acres of land. There are no existing residences within a mile of the planned terminal, but the proposed pipeline would cross within 50 feet of 179 residences and 56 other buildings, it indicated.

Mid-Atlantic Express LLC, an AES division which proposes constructing an 88-mile pipeline from the LNG terminal to Eagle, Pa., has filed site-specific plans for residences within 25 feet of construction, the final EIS said. But FERC's staff found that the plans lacked detail and sufficient mitigation measures, it added. "Pipeline construction could also affect wells and septic systems; therefore, we have recommended that Mid-Atlantic Express file site-specific plans for residences within 50 feet of the pipeline construction work space as well as measures for mitigating impacts to wells, septic systems and other utilities," it said.

Camps, parks and trails

The pipeline's construction also could have adverse impacts on several camps, parks and trails, it continued. "Many of the construction impacts would be temporary; however some scenic watersheds would be permanently impacted," it said.

AES also would be required to develop and implement an emergency response plan which would involve state and local agencies and municipalities, including a cost-sharing plan and a transit management plan, according to the final EIS. The company also would have to meet requirements of FERC, the Coast Guard and other federal agencies, it said.

Ruppersberger said that the Coast Guard issued a report earlier this year which found that AES does not appear to take security seriously and assumes that the Coast Guard will handle all security at taxpayer expense. "In addition, the company . . . wants Maryland taxpayers to foot much of the bill for any security changes that may need to be implemented. This is unfair because the natural gas will be pumped out of state," he said.

FERC's final EIS said that the Coast Guard's Feb. 25 Waterway Suitability Report identifies specific risk mitigation measures which would be needed to responsibly manage maritime safety and security risks. "Accordingly, we have recommended that the proposed facility comply with all requirements set forth by the Coast Guard," it said.

It noted that since the draft EIS was issued in late April, US Commerce Secretary Carlos Gutierrez issued a finding that the project, if approved, would be consistent with the Coastal Zone Management Act, as necessary for the establishment of safety and security zones for LNG traffic in Maryland and Virginia waters.

FERC said that commissioners would consider the staff's recommendations in the final EIS when they make a final decision on the proposed project.

Contact Nick Snow at nicks@pennwell.com

Related Articles

PHMSA proposes pipeline accident notification regulations

07/02/2015 The US Pipeline and Hazardous Materials Safety Administration has proposed new federal oil and gas pipeline accident and notification regulations. ...

Quicksilver Canada gets LNG export approval

07/02/2015 Quicksilver Resources Canada Inc. has received approval from the National Energy Board of Canada to export 20 million tonnes/year of LNG from a pos...

BP to settle federal, state Deepwater Horizon claims for $18.7 billion

07/02/2015 BP Exploration & Production Inc. has agreed in principle to settle all federal and state claims arising from the 2010 Deepwater Horizon inciden...

API to issue recommended practice to address pipeline safety

07/01/2015 The American Petroleum Institute expects to issue a new recommended practice in another few weeks that addresses pipeline safety issues, but the tr...

Woodside-led Browse FLNG venture enters FEED phase

07/01/2015 The Woodside Petroleum Ltd.-led Browse LNG joint venture has entered the front-end engineering and design phase for a floating LNG (FLNG) developme...

FWS issues Shell letter of authorization on Chukchi Sea lease

07/01/2015 The US Fish & Wildlife Service issued Shell Gulf of Mexico Inc. a letter of authorization (LOA) related to the potential disturbance of polar b...

Case for Keystone XL has grown stronger, TransCanada tells Kerry

06/30/2015 Canada is taking strong steps toward combating climate change, and the proposed Keystone XL pipeline crude oil pipeline remains in the US national ...

Court rejects BP, Anadarko Macondo appeals

06/30/2015 BP PLC and Anadarko Petroleum Corp. have lost separate appeals to the US Supreme Court to overturn a lower-court decision expanding their financial...

Senate Democrats outline broad energy goals to nation’s governors

06/30/2015 Forty-five US Senate Democrats outlined broad energy policy goals including more clean energy technology investments, infrastructure improvement, a...
White Papers

2015 Global Engineering Information Management Solutions Competitive Strategy Innovation and Leadership Award

The Frost & Sullivan Best Practices Awards recognise companies in a variety of regional and global...
Sponsored by

Three Tips to Improve Safety in the Oil Field

Working oil fields will always be tough work with inherent risks. There’s no getting around that. Ther...
Sponsored by

Pipeline Integrity: Best Practices to Prevent, Detect, and Mitigate Commodity Releases

Commodity releases can have catastrophic consequences, so ensuring pipeline integrity is crucial for p...
Sponsored by

AVEVA’s Digital Asset Approach - Defining a new era of collaboration in capital projects and asset operations

There is constant, intensive change in the capital projects and asset life cycle management. New chall...
Sponsored by

Transforming the Oil and Gas Industry with EPPM

With budgets in the billions, timelines spanning years, and life cycles extending over decades, oil an...
Sponsored by

Asset Decommissioning in Oil & Gas: Transforming Business

Asset intensive organizations like Oil and Gas have their own industry specific challenges when it com...
Sponsored by

Squeezing the Green: How to Cut Petroleum Downstream Costs and Optimize Processing Efficiencies with Enterprise Project Portfolio Management Solutions

As the downstream petroleum industry grapples with change in every sector and at every level, includin...
Sponsored by

7 Steps to Improve Oil & Gas Asset Decommissioning

Global competition and volatile markets are creating a challenging business climate for project based ...
Sponsored by
Available Webcasts


OGJ's Midyear Forecast 2015

When Fri, Jul 10, 2015

This webcast is to be presented by OGJ Editor Bob Tippee and Senior Economic Editor Conglin Xu.  They will summarize the Midyear Forecast projections in key categories, note important changes from January’s forecasts, and examine reasons for the adjustments.

register:WEBCAST


Predictive Analytics in your digital oilfield - Optimize Production Yield and Reduce Operational Costs

When Tue, Jul 7, 2015

Putting predictive analytics to work in your oilfield can help you anticipate failures, plan and schedule work in advance, eliminate emergency work and catastrophic failures, and at the same time you can optimize working capital and improve resource utilization.  When you apply analytic capabilities to critical production assets it is possible to reduce non-productive time and increase your yield.

Learn how IBM's analytics capabilities can be applied to critical production assets with the goal of reducing non-productive time, increasing yield and reducing operations costs.

register:WEBCAST



On Demand

Cognitive Solutions for Upstream Oil and Gas

Fri, Jun 12, 2015

The oil & gas sector is under pressure on all sides. Reserves are limited and it’s becoming increasingly expensive to find and extract new resources. Margins are already being squeezed in an industry where one wrong decision can cost millions. Analyzing data used in energy exploration can save millions of dollars as we develop ways to predict where and how to extract the world’s massive energy reserves.

This session with IBM Subject Matter Experts will discuss how IBM Cognitive Solutions contribute to the oil and gas industry using predictive analytics and cognitive computing, as well as real time streaming for exploration and drilling.

register:WEBCAST


The Alternative Fuel Movement: Four Need-to-Know Excise Tax Complexities

Thu, Jun 4, 2015

Discussion on how to approach, and ultimately embrace, the alternative fuel market by pulling back the veil on excise tax complexities. Taxes may be an aggravating part of daily operations, but their accuracy is crucial in your path towards business success.

register:WEBCAST


Emerson Micro Motion Videos

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected