Enbridge advances two pipeline projects

By OGJ editors
HOUSTON, Jan. 30 -- Enbridge Energy Partners LP has let a contract to Gulf Interstate Engineering Co. for first-phase preliminary engineering services for sections of the proposed Alberta Clipper oil pipeline and the Southern Lights diluent pipeline, which is under development in the US. The contract value was not disclosed.

The section of the Alberta Clipper project covered under the Gulf Interstate contract includes 325 miles of 36-in. pipe that will extend from the US-Canadian border to Superior, Wis. Also covered are three 15,000-hp pump stations.

The portion of the Southern Lights project covered under the contract includes a 190-mile, 20-in. line from Superior, Wis., to Clearbrook, Minn., a 6,000 hp pump station, and flow reversal at three existing pump stations. The complete $920 million Southern Lights project involves installation of 475 miles of pipe that will transport diluent (OGJ Online, Aug. 29, 2006).

This contract award follows Enbridge's announcement that it has received industry support to proceed with construction of two projects as additions to the Enbridge common carrier mainline system. The $2 billion (2006 US dollars) Alberta Clipper project, which Enbridge initially introduced in February 2006, is one of these. The other is a $3 million (Can.) Line 4 Extension project, which is designed to eliminate a potential capacity bottleneck on the mainline system between Edmonton and Hardisty, Alta.

The extension project involves the construction of 85 miles of 36-in. segments of pipe that will connect existing 48-in. pipe segments that have been idle between Edmonton and Hardisty and move the origination point of Line 4 from Hardisty back to Edmonton. Capacity of the extension will be 880,000 b/d to match current Line 4 capacity.

The Alberta Clipper project involves the construction of a 36-in., 990-mile crude line from Hardisty, Alta., to Superior, Wis., primarily following Enbridge's existing right-of-way. The line's initial capacity will be 450,000 b/d and ultimate capacity will be about 800,000 b/d.

The Canadian portion of Alberta Clipper is expected to cost about $1.5 billion (Can.) and the US portion is expected to cost $8 million (US).

Both the Alberta Clipper and the Line 4 Extension projects will be integrated with, and form part of the existing Enbridge system in Canada, and the company's Lakehead system in the US.

Enbridge and the Canadian Association of Petroleum Producers will attempt during this quarter to finalize the scope and other details of these two projects, which remain subject to company board approvals, as well as various Canadian and US regulatory approvals and permits.

The company plans also to immediately begin long lead-time activities, such as finalizing steel pipe commitments, public consultation, preparatory work for right-of-way, and working space access agreements and permits to facilitate an anticipated in-service date for the Line 4 Extension of late 2008, and for Alberta Clipper, late 2009 to mid-2010.

Enbridge said that in order to balance the increased capacity into Superior, an expansion of the 42-in. Southern Access line to Chicago will be undertaken at an estimated cost of $1 million. The Southern Access project is being developed in two stages providing a capacity of 146,000 b/d by first quarter 2008 and an additional 254,000 b/d by first quarter 2009. This project is expandable to 1.2 million b/d with expansions timed concurrently with the Alberta Clipper project.

Related Articles

Pennsylvania governor asks Obama for stronger crude-by-rail rules

03/02/2015 Noting that 60-70 trains/week carry Bakken crude oil across Pennsylvania to the Philadelphia area or other East Coast refineries, Gov. Tom Wolf (D)...

Gassco takes over as operator of Knarr pipeline

03/02/2015 Gassco has taken over as operator of the Knarr pipeline, which will transport rich gas to the Shell-Esso Gas and Liquids (Segal) system and St. Fer...

Vibration modeling improves pipeline performance, costs

03/02/2015 Modeling neural networks to vibration patterns of operating gas turbines and then applying these models to the same turbines' future performance an...

BP: Global energy demand to jump 37% by 2035

03/02/2015 Global demand for energy is expected to rise by 37% from 2013 to 2035, or by an average of 1.4%/year, due in large part to ongoing economic expansi...

Obama vetoes bill approving Keystone XL crude oil pipeline

03/02/2015 US President Barack Obama vetoed S. 1, authorizing construction of the proposed Keystone XL crude oil pipeline, saying that Congress had attempted ...

OGJ Newsletter

03/02/2015

International news for oil and gas professionals

Smart phone technology enhances field studies

03/02/2015

Throughout northern Oklahoma and Kansas, the Mississippian Lime has emerged as a significant unconventional oil play.

IHS: Crude transported by Keystone XL would be consumed in US

03/02/2015 Most, if not all, of the crude oil that would be transported via the proposed Keystone XL pipeline to the US Gulf Coast would not be exported, and ...

Magellan, PAA form Saddlehorn crude pipeline joint venture

02/27/2015 Magellan Midstream Partners LP and Plains All American Pipeline LP have formed Saddlehorn Pipeline Co., a 50-50 limited liability joint venture, to...

White Papers

Transforming the Oil and Gas Industry with EPPM

With budgets in the billions, timelines spanning years, and life cycles extending over decades, oil an...
Sponsored by

Asset Decommissioning in Oil & Gas: Transforming Business

Asset intensive organizations like Oil and Gas have their own industry specific challenges when it com...
Sponsored by

Squeezing the Green: How to Cut Petroleum Downstream Costs and Optimize Processing Efficiencies with Enterprise Project Portfolio Management Solutions

As the downstream petroleum industry grapples with change in every sector and at every level, includin...
Sponsored by

7 Steps to Improve Oil & Gas Asset Decommissioning

Global competition and volatile markets are creating a challenging business climate for project based ...
Sponsored by

The impact of aging infrastructure in process manufacturing industries

Process manufacturing companies in the oil and gas, utilities, chemicals and natural resource industri...
Sponsored by

What is System Level Thermo-Fluid Analysis?

This paper will explain some of the fundamentals of System Level Thermo-Fluid Analysis and demonstrate...

Accurate Thermo-Fluid Simulation in Real Time Environments

The crux of any task undertaken in System Level Thermo-Fluid Analysis is striking a balance between ti...

6 ways for Energy, Chemical and Oil and Gas Companies to Avert the Impending Workforce Crisis

As many as half of the skilled workers in energy, chemical and oil & gas industries are quickly he...
Sponsored by

Available Webcasts



Global LNG: Adjusting to New Realties

When Fri, Mar 20, 2015

Oil & Gas Journal’s March 20, 2015, webcast will look at how global LNG trade will be affected over the next 12-24 months by falling crude oil prices and changing patterns and pressures of demand. Will US LNG production play a role in balancing markets? Or will it add to a growing global oversupply of LNG for markets remote from easier natural gas supply? Will new buyers with marginal credit, smaller requirements, or great need for flexibility begin to look attractive to suppliers? How will high-cost, mega-projects in Australia respond to new construction cost trends?

register:WEBCAST


US Midstream at a Crossroads

When Fri, Mar 6, 2015

Oil & Gas Journal’s Mar. 6, 2015, webcast will focus on US midstream companies at an inflection point in their development in response to more than 6 years shale oil and gas production growth. Major infrastructure—gas plants, gathering systems, and takeaway pipelines—have been built. Major fractionation hubs have expanded. Given the radically changed pricing environment since mid-2014, where do processors go from here? What is the fate of large projects caught in mid-development? How to producers and processors cooperate to ensure a sustainable and profitable future? This event will serve to set the discussion table for the annual GPA Convention in San Antonio, Apr. 13-16, 2015.

This event is sponsored by Leidos Engineering.

register:WEBCAST



On Demand

The Future of US Refining

Fri, Feb 6, 2015

Oil & Gas Journal’s Feb. 6, 2015, webcast will focus on the future of US refining as various forces this year conspire to pull the industry in different directions. Lower oil prices generally reduce feedstock costs, but they have also lowered refiners’ returns, as 2015 begins with refined products priced at lows not seen in years. If lower per-barrel crude prices dampen production of lighter crudes among shale plays, what will happen to refiners’ plans to export more barrels of lighter crudes? And as always, refiners will be affected by government regulations, particularly those that suppress demand, increase costs, or limit access to markets or supply.

register:WEBCAST


Oil & Gas Journal’s Forecast & Review/Worldwide Pipeline Construction 2015

Fri, Jan 30, 2015

The  Forecast & Review/Worldwide Pipeline Construction 2015 Webcast will address Oil & Gas Journal’s outlooks for the oil market and pipeline construction in a year of turbulence. Based on two annual special reports, the webcast will be presented by OGJ Editor Bob Tippee and OGJ Managing Editor-Technology Chris Smith.
The Forecast & Review portion of the webcast will identify forces underlying the collapse in crude oil prices and assess prospects for changes essential to recovery—all in the context of geopolitical pressures buffeting the market.

register:WEBCAST


Emerson Micro Motion Videos

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected