Seneca Resources Corp., Houston, has awarded J. Ray McDermott SA a turnkey contract for the design engineering, procurement, structural fabrication, process outfitting, and load-out of a three-pile jacket and deck to be installed in 124 ft of water on Viosca Knoll Block 432 in the Gulf of Mexico.

By OGJ editors
HOUSTON, Dec. 19 -- Seneca Resources Corp., Houston, has awarded J. Ray McDermott SA a turnkey contract for the design engineering, procurement, structural fabrication, process outfitting, and load-out of a three-pile jacket and deck to be installed in 124 ft of water on Viosca Knoll Block 432 in the Gulf of Mexico.

The contract, expected to be completed by May 2006, covers the jacket, deck with process facilities, piles, and heliport.

Pinnacle Engineering Inc. will provide the detail design and equipment procurement.