CSB cites six safety issues in BP refinery explosion

By OGJ editors
HOUSTON, Oct. 28 -- Investigators from the US Chemical Safety and Hazard Investigation Board (CSB) Oct. 27 identified six key safety issues underlying the Mar. 23 explosions and fire at BP PLC's 446,400 b/cd Texas City, Tex., refinery. The incident, which was contained within the plant's 24,300 b/cd isomerization unit, killed 15 workers and injured 170 others (OGJ Online, Mar. 23, 2005).

The six identified safety issues were:

-- Trailers were placed in an unsafe location, too close to an isom process unit. All of the fatalities occurred in and around trailers that were as close as 121 ft from the release of flammable material from a blowdown drum. One trailer 600 ft from the explosions was heavily damaged, and 39 other trailers were either damaged or destroyed.

-- The unit's raffinate splitter should not have been started up due to existing malfunctions of the level indicator, level alarm, and a control valve.

-- The raffinate splitter tower had a history of abnormal start-ups that included recurrent high liquid levels and pressures.

-- On Mar. 23, a blowdown drum vented highly flammable material directly to the atmosphere. The drum was never connected to a flare since its construction in the 1950s. The previous owner of the refinery, Amoco Corp., replaced the isom unit blowdown drum in 1997 with identical equipment; Amoco refinery safety standards recommended connecting the drum to a flare when such major modifications were undertaken, but this was not done.

-- Between 1995 and Mar. 23, 2005, there were four other serious releases of flammable material from the isom blowdown drum and stack that led to ground-level vapor clouds, none of which ignited.

-- In 1992, the US Department of Labor's Occupational Safety and Health Administration cited a similar blowdown drum and stack at the Texas City plant as unsafe because it vented flammable material directly to the atmosphere, but the citation was dropped and the drum was not connected to a flare system.

In May, BP issued a statement blaming personnel mistakes for the refinery explosion. A BP investigative team concluded that personnel failures before and during start-up of the isom unit in the plant led to the explosion and fire (OGJ Online, May 18, 2005).

This month, BP agreed to pay more than $21 million in penalties under a settlement agreement with OSHA for violations connected with the explosion (OGJ Online, Oct. 10, 2005).

What happened
CSBIB investigators released three computer animations of the start-up of the isom unit, the vapor cloud formation, and the subsequent explosions. "The simulations showed a vapor cloud that blanketed much of the nearly 5-acre isom unit just before the cloud was ignited, most likely by an idling diesel pickup truck," investigators said.

The process simulation depicts liquid hydrocarbon flows through a complex of piping connecting a heat exchanger, a furnace, the raffinate splitter tower, and the blowdown drum. "As the temperature and fluid levels increase inside the tower, the animation shows pressure-relief valves directing overflow to the blowdown drum and attached vent stack," investigators said. "The drum rapidly fills, finally causing a geyser-like release of flammable liquids from the top of the vent stack. The vaporizing liquid falls to the ground, where it forms a vapor cloud."

Don Holmstrom, CSB lead investigator, noted, "The first rule of oil refinery safety is to keep the flammable, hazardous materials inside piping and equipment. A properly designed and sized knockout drum and flare system would have safely contained the liquids and burned off the flammable vapors, preventing a release to the atmosphere."

Investigators found evidence that BP evaluated connecting the raffinate splitter to a flare system in 2002 but ultimately decided against it, Holmstrom said. Following the incident, BP said it would eliminate blowdown stacks that vent directly to the atmosphere at all US refineries.

Investigators presented new details on the 16 previous start-ups of the raffinate splitter from 2000 onward. They found 8 start-ups with tower pressures of at least double the normal value and 13 start-ups with excess liquid levels. BP did not investigate any of these abnormal start-ups.

"Investigations of these incidents could have resulted in improvements in tower design, instrumentation, procedures, and controls," Holmstrom stated.

He said there was no supervisor with appropriate experience overseeing the unit's start-up. "Operators did not follow the requirements of start-up procedures, including opening the level control valve for the splitter tower," he said. "This omission allowed the tower level to rise rapidly for 3 hr to 15 times its normal level. Operators were misled by the malfunctioning level indicator on the tower and a separate high-level alarm, which failed to activate."

Investigators also stated that a number of equipment problems made it unsafe to start up the raffinate splitter. "Proper working order of key process instrumentation was not checked as required by the start-up procedure," Holmstrom stated, adding, "Managers turned away technicians and signed off on the instrument tests as if they had been done."

Investigators also found that BP's traffic policy allowed vehicles unrestricted access near process units. On Mar. 23, there were running vehicles, including a diesel pickup truck, as close as 25 ft from the blowdown drum. "A total of 55 vehicles were in the vicinity of the drum, investigators determined, and one likely served as the ignition source for the explosions," Holmstrom said.

CSB earlier this week issued two recommendations to leading US petrochemical trade organizations, calling on the American Petroleum Institute to develop new safety guidance that would establish minimum distances for occupied trailers away from hazardous areas of process plants. The board also called on API and the National Petrochemical & Refiners Association to immediately contact their members urging "prompt action to ensure the safe placement of occupied trailers away from hazardous areas of process plants," before the new API safety guidance is completed.

A final public report of the investigation is expected in 2006.

Related Articles

API to issue recommended practice to address pipeline safety

07/01/2015 The American Petroleum Institute expects to issue a new recommended practice in another few weeks that addresses pipeline safety issues, but the tr...

Shell Midstream Partners takes interest in Poseidon oil pipeline

07/01/2015 Shell Midstream Partners LP has completed its acquisition of 36% equity interest in Poseidon Oil Pipeline Co. LLC from Equilon Enterprises LLC, a s...

SIBUR plans MTBE expansion at Togliattikauchuk

07/01/2015 Russian conglomerate OAO SIBUR Holding, Moscow, has started preparatory work for a project designed to expand production capacity for methyl tertia...

Shell makes FID on Appomattox deepwater development in Gulf of Mexico

07/01/2015 Royal Dutch Shell PLC has taken a final investment decision (FID) on the Appomattox deepwater development, authorizing construction and installatio...

MARKET WATCH: Oil prices decline as US crude inventories post first gain in 9 weeks

07/01/2015 Oil prices on July 1 surrendered much of their gains from the day before after the release of a government report showing the first rise in US crud...

Woodside-led Browse FLNG venture enters FEED phase

07/01/2015 The Woodside Petroleum Ltd.-led Browse LNG joint venture has entered the front-end engineering and design phase for a floating LNG (FLNG) developme...

FWS issues Shell letter of authorization on Chukchi Sea lease

07/01/2015 The US Fish & Wildlife Service issued Shell Gulf of Mexico Inc. a letter of authorization (LOA) related to the potential disturbance of polar b...

USGS: Water usage for fracturing varies widely across shale plays

07/01/2015 The volume of water required to hydraulically fracture wells varies widely across the country, according to the first national analysis and map of ...

Case for Keystone XL has grown stronger, TransCanada tells Kerry

06/30/2015 Canada is taking strong steps toward combating climate change, and the proposed Keystone XL pipeline crude oil pipeline remains in the US national ...
White Papers

Three Tips to Improve Safety in the Oil Field

Working oil fields will always be tough work with inherent risks. There’s no getting around that. Ther...
Sponsored by

Pipeline Integrity: Best Practices to Prevent, Detect, and Mitigate Commodity Releases

Commodity releases can have catastrophic consequences, so ensuring pipeline integrity is crucial for p...
Sponsored by

AVEVA’s Digital Asset Approach - Defining a new era of collaboration in capital projects and asset operations

There is constant, intensive change in the capital projects and asset life cycle management. New chall...
Sponsored by

Transforming the Oil and Gas Industry with EPPM

With budgets in the billions, timelines spanning years, and life cycles extending over decades, oil an...
Sponsored by

Asset Decommissioning in Oil & Gas: Transforming Business

Asset intensive organizations like Oil and Gas have their own industry specific challenges when it com...
Sponsored by

Squeezing the Green: How to Cut Petroleum Downstream Costs and Optimize Processing Efficiencies with Enterprise Project Portfolio Management Solutions

As the downstream petroleum industry grapples with change in every sector and at every level, includin...
Sponsored by

7 Steps to Improve Oil & Gas Asset Decommissioning

Global competition and volatile markets are creating a challenging business climate for project based ...
Sponsored by

The impact of aging infrastructure in process manufacturing industries

Process manufacturing companies in the oil and gas, utilities, chemicals and natural resource industri...
Sponsored by
Available Webcasts


OGJ's Midyear Forecast 2015

When Fri, Jul 10, 2015

This webcast is to be presented by OGJ Editor Bob Tippee and Senior Economic Editor Conglin Xu.  They will summarize the Midyear Forecast projections in key categories, note important changes from January’s forecasts, and examine reasons for the adjustments.

register:WEBCAST


Predictive Analytics in your digital oilfield - Optimize Production Yield and Reduce Operational Costs

When Tue, Jul 7, 2015

Putting predictive analytics to work in your oilfield can help you anticipate failures, plan and schedule work in advance, eliminate emergency work and catastrophic failures, and at the same time you can optimize working capital and improve resource utilization.  When you apply analytic capabilities to critical production assets it is possible to reduce non-productive time and increase your yield.

Learn how IBM's analytics capabilities can be applied to critical production assets with the goal of reducing non-productive time, increasing yield and reducing operations costs.

register:WEBCAST



On Demand

Cognitive Solutions for Upstream Oil and Gas

Fri, Jun 12, 2015

The oil & gas sector is under pressure on all sides. Reserves are limited and it’s becoming increasingly expensive to find and extract new resources. Margins are already being squeezed in an industry where one wrong decision can cost millions. Analyzing data used in energy exploration can save millions of dollars as we develop ways to predict where and how to extract the world’s massive energy reserves.

This session with IBM Subject Matter Experts will discuss how IBM Cognitive Solutions contribute to the oil and gas industry using predictive analytics and cognitive computing, as well as real time streaming for exploration and drilling.

register:WEBCAST


The Alternative Fuel Movement: Four Need-to-Know Excise Tax Complexities

Thu, Jun 4, 2015

Discussion on how to approach, and ultimately embrace, the alternative fuel market by pulling back the veil on excise tax complexities. Taxes may be an aggravating part of daily operations, but their accuracy is crucial in your path towards business success.

register:WEBCAST


Emerson Micro Motion Videos

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected