FERC approves Sabine Pass LNG terminal

By OGJ editors

HOUSTON, Dec. 22 -- The US Federal Energy Regulatory Commission has approved construction of the 2.6 bcfd LNG regasification terminal proposed in Cameron Parish, La., by Sabine Pass LNG LP, a unit of Cheniere Energy Inc., Houston.

FERC also approved construction of a 26-mile pipeline proposed by Cheniere Sabine Pass Pipeline Co. connecting the LNG terminal to an existing gas pipeline.

Sabine Pass LNG has said construction of the terminal might begin in first quarter 2005 (OGJ, Sept. 20, 2004, Newsletter).

The project is the third new US LNG terminal to receive FERC approval. The commission approved the Cameron LNG LLC project by Sempra Energy LNG Corp. near Hackberry, La., in September 2003, and the Freeport LNG Development LP terminal on Quintana Island, near Freeport, Tex., in June 2004.

Related Articles

Increased gas production from shale rewires global supply grid

10/01/2013 DENVER, Colo.—"Unconventional gas is changing the dynamic within the global gas trade network," Elizabeth Spomer, senior vice-president, ...

DOE approves Dominion Cove Point LNG exports to non-FTA countries

09/23/2013 The US Department of Energy approved Dominion Cove Point LP's application to export LNG from its terminal in Calvert County, Md., to countries that...

Demand and prices fall

12/29/2008 Even as a winter storm dumped snow and ice on the US Midwest and East Coast during Christmas week, markets remained unconvinced OPEC can cut produc...

MARKET WATCH: Energy demand, prices both plummet

12/23/2008 The front-month February contract for benchmark US crudes fell 6% to less than $40/bbl Dec. 22 amid market fears OPEC cannot cut production fast en...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected