Tangguh LNG awards second compressor train contract in Indonesia

By OGJ editors

HOUSTON, July 22 -- Tangguh LNG partners have awarded GE Energy a contract to supply a second compressor train for the project in Bintuni Bay Regency, Papua Province, Indonesia.

Last year, GE was selected to supply the first compressor train for the project. When both trains are completed, the new facility, which is owned by BP Tangguh LNG Indonesia, will have a gas liquefaction capacity of at least 7 million tonnes/year of LNG.

GE Energy's Florance, Italy-based oil and gas unit will supply the two main refrigerant turbo compressor strings for the second compressor train. The mixed refrigerant string will include one low-pressure axial compressor and one medium-pressure centrifugal compressor. The propane string will include one low-pressure and one high-pressure barrel centrifugal compressor.

The turbo compressor strings are slated for shipment in 2005.

Related Articles

Senate Republicans introduce energy amendment to jobs bill

04/02/2014 Three Republican members of the US Senate Energy and Natural Resources Committee introduced legislation that would approve the Keystone XL crude oi...

OGJ Newsletter

03/31/2014

International news for oil and gas professionals

LNG exports' immediate geopolitical impacts limited, senators told

03/31/2014

Direct geopolitical impacts from the US authorizing LNG exports more quickly would be limited, witnesses told a US Senate committee.

NGSA asks Congress to pass bills facilitating LNG exports

03/27/2014 The Natural Gas Supply Association called on Congress to support legislation that would facilitate more LNG exports. “Exporting LNG overseas will h...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected