Precommissioning completed on Shell's Goldeneye development

By OGJ editors

HOUSTON, Dec. 2 -- Shell UK Exploration & Production, operator of Goldeneye field in the Outer Moray Firth area of the UK Central North Sea, has successfully completed precommissioning 101 km of 20-in. export pipeline and 4-in. mono-ethylene glycol pipeline from the field to its St. Fergus, Scotland gas plant.

Halliburton Energy Services, a business unit of Halliburton, performed the work through its Pipeline and Process Services product service line.

Work included flooding, cleaning, gauging, high pressure flushing, and hydrotesting the pipelines from onshore to enable their transport of gas and condensate from the field to the plant.

Saipem UK installed the two pipelines simultaneously, using its Castoro Sei pipelay vessel in water 120 m deep.

Related Articles

Christie calls for N. American energy system improvements

09/05/2014 Mexico, Canada, and the US will need to significantly increase investments in energy systems if they expect to achieve the full benefits of a North...

Williams holding open season on Western Marcellus Transco expansion

09/05/2014 Williams is holding an open season for its Western Marcellus Pipeline Project, an expansion of the Transco interstate pipeline to provide increment...

Pembina files to build Fox Creek-to-Namao Junction Phase III segment

09/05/2014 Pembina Pipeline Corp. has filed with the Alberta Energy Regulator (AER) for the Fox Creek, Alta., to Namao Junction, Alta., segment of its previou...

KMEP launches binding open season for Utopia pipeline

09/04/2014 Kinder Morgan Energy Partners LP (KMEP) has launched a binding open season to solicit commitments for the Utica-to-Ontario Pipeline Access (Utopia)...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected