Precommissioning completed on Shell's Goldeneye development

By OGJ editors

HOUSTON, Dec. 2 -- Shell UK Exploration & Production, operator of Goldeneye field in the Outer Moray Firth area of the UK Central North Sea, has successfully completed precommissioning 101 km of 20-in. export pipeline and 4-in. mono-ethylene glycol pipeline from the field to its St. Fergus, Scotland gas plant.

Halliburton Energy Services, a business unit of Halliburton, performed the work through its Pipeline and Process Services product service line.

Work included flooding, cleaning, gauging, high pressure flushing, and hydrotesting the pipelines from onshore to enable their transport of gas and condensate from the field to the plant.

Saipem UK installed the two pipelines simultaneously, using its Castoro Sei pipelay vessel in water 120 m deep.

Related Articles

ETP unit gets FERC approval for gas exports to Mexico

03/21/2014 Energy Transfer Partners LP unit Houston Pipe Line Co. LP (HLPC) has received approval from the US Federal Energy Regulatory Commission to build a ...

Millennium Pipeline appoints president

03/20/2014 Millennium Pipeline Co. LLC has selected Joseph Shields as its president. He succeeds Rocco D’Alessandro, who held the position beginning in May 20...

Shah Deniz II, South Caucasus Pipeline contracts awarded

03/20/2014 The Shah Deniz and South Caucasus Pipeline consortia awarded project management and construction contracts for the development of Shah Deniz Stage ...

MARKET WATCH: NYMEX crude prices rise on Seaway pipeline expansion news

03/19/2014 Crude oil futures prices rose on the New York market Mar. 18 after Enterprise Products Partners LP told analysts and investors that an expanded Sea...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected