Precommissioning completed on Shell's Goldeneye development

By OGJ editors

HOUSTON, Dec. 2 -- Shell UK Exploration & Production, operator of Goldeneye field in the Outer Moray Firth area of the UK Central North Sea, has successfully completed precommissioning 101 km of 20-in. export pipeline and 4-in. mono-ethylene glycol pipeline from the field to its St. Fergus, Scotland gas plant.

Halliburton Energy Services, a business unit of Halliburton, performed the work through its Pipeline and Process Services product service line.

Work included flooding, cleaning, gauging, high pressure flushing, and hydrotesting the pipelines from onshore to enable their transport of gas and condensate from the field to the plant.

Saipem UK installed the two pipelines simultaneously, using its Castoro Sei pipelay vessel in water 120 m deep.

Related Articles

Total, CNOOC sign LNG cooperation agreement

03/26/2014 Total SA and China National Offshore Oil Corp. (CNOOC) have reached an LNG cooperation agreement that will expand upon the companies’ existing 15-y...

KMEP to build Permian carbon dioxide pipeline

03/26/2014 Kinder Morgan Energy Partners LP will build and operate a 213-mile, 16-in. OD pipeline to transport carbon dioxide from its St. Johns source field ...

Lake Charles LNG export project partners file FERC application

03/26/2014 Trunkline LNG Co. LLC and Trunkline LNG Export LLC, both wholly owned subsidiaries of Energy Transfer Equity LP and Energy Transfer Partners LP, ha...

LNG exports’ immediate geopolitical impacts limited, senators told

03/26/2014 Direct geopolitical impacts from the US authorizing LNG exports more quickly would be limited, witnesses told a US Senate committee. But global mar...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected