Ormen Lange group awards Aker Kværner FEED contract for processing plant

By OGJ editors

HOUSTON, Mar. 19 -- Norsk Hydro ASA, development operator for Ormen Lange field in the Norwegian Sea, has selected Aker Kværner, Lysaker, Norway, to receive a contract worth 950 million kroner for engineering and design of the project's onshore Nyhamna processing plant near Aukra, in Møre og Romsdal County, Norway.

The contract is for front-end engineering design, engineering, procurement, and construction management assistance. The work will enable the consortium to establish an investment-decision cost estimate before submitting a formal plan for development and operation (PDO).

The Nyhamna development, due for completion when Ormen Lange field comes on stream in 2007, includes the process plant, utility systems, slug catchers, a tank farm, and power supply and distribution. EPC contracts for these other installations will be awarded during 2003-05, Norsk Hydro said.

Pipeline plans
The Ormen Lange project also will require one of the most extensive subsea gas export pipeline on the Norwegian continental shelf, a two-part pipeline with a combined length of 1,200 km from the onshore processing plant to the UK via Sleipner field.

The Ormen Lange licensees chose the route Dec. 18 (OGJ Online, Dec. 23, 2002) for the export pipeline—from the processing plant at Aukra to the Sleipner installation in the North Sea, and from Sleipner to Easington/Dimlington, UK—and gave approval in February to proceed with pipeline construction.

Norsk Hydro plans in June to submit to Norwegian authorities a plan for the installation and operation (PIO) of the most southerly stretch of the pipeline system—between Sleipner and Easington/Dimlington in the southeastern UK.

A corresponding PIO for the northerly section, between Sleipner and the Nyhmna plant, is scheduled for delivery to authorities by October, together with the PDO for deepwater Ormen Lange field itself, which lies 140 km west of Kristiansund, Norway in 1,000 m of water.

Ormen Lange needs pipeline capacity of at least 60 million standard cu m/day. In addition, there is transport capacity demand in other parts of the system for gas from other fields.

"The total export pipeline system tied into Ormen Lange will be the most significant pipeline project ever in the Norwegian offshore sector," a consortium spokesperson said.

The total Ormen Lange investment, including field development and transportation pipelines, is estimated to be 55 billion kroner (2002). The field is the first deepwater development project on the Norwegian Continental Shelf.

"The investment demands large parts of the world's pipeline-laying capacity in 2005 and 2006," says Bengt Lie Hansen, Hydro's head of mid-Norway exploration and development. "Ormen Lange will increase Norwegian gas export(s) by 25%, making Norway the world's next largest gas exporter after Russia," he said.

First production from Ormen Lange is planned for October 2007, with gas production scheduled to continue for 30-40 years. AS Norske Shell is the production phase operator. The field's production is expected to peak at 20 billion standard cu m/year of natural gas, about 20% of the total anticipated Norwegian gas production in 2010, Norsk Hydro said.

The estimated gas reserves on Ormen Lange are 375 billion standard cu m of dry gas and 22 million standard cu m of condensate, making it the largest undeveloped gas field on the shelf.

Developer Norsk Hydro holds a 17.956% interest share in the field and Norske Shell 17.2%. Other shareholders are Petoro AS 36%, Statoil ASA 10.774%, Esso Norge AS 7.182%, and BP PLC 10.888%.

Related Articles

Senate Banking Committee’s crude export debate breaks along party lines

07/28/2015 Congressional committee debate over the 40-year ban on exporting US-produced crude oil continued to break largely along party lines as the US Senat...

Financing set for gas line in northern Mexico

07/28/2015 Financing is set for construction of a 289-mile pipeline that will carry natural gas produced in Texas to power plants in Mexico, reports Milbank, ...

Husky assesses options for West White Rose extension project

07/28/2015 The Canada-Newfoundland and Labrador Offshore Petroleum Board said it has provided “conditional approval” of a development plan by Husky Energy Inc...

Canada’s NEB approves Orca LNG export license

07/28/2015 Canada’s National Energy Board has approved an application by Orca LNG Ltd., Cypress, Tex., for a 25-year natural gas export license (OGJ Online, J...

UK awards 41 more licenses in offshore round

07/28/2015

The UK government has awarded 41 licenses for exploration and production in the second tranche of the 28th Offshore Licensing Round.

CBM producer Walter Energy files for Chapter 11

07/28/2015 Walter Energy Inc., Birmingham, Ala., and its US subsidiaries filed for restructuring under Chapter 11 bankruptcy in the US Northern District Court...

MARKET WATCH: Oil futures maintain downward momentum

07/28/2015 Light, sweet crude oil futures prices fell July 27 to settle at less than $48/bbl on the New York market while Brent prices on the London market pl...

Excelerate gets FERC okay for Aguirre offshore GasPort project

07/27/2015 Excelerate Energy LP, The Woodlands, Tex., has been granted authorization by the US Federal Energy Regulatory Commission, in cooperation with the P...

Encana books impairment charge, maintains 2015 budget

07/27/2015 Encana Corp., Calgary, reported a $1.3 billion impairment charge for the second quarter, which executives said reflected a decline in oil and natur...
White Papers

2015 Global Engineering Information Management Solutions Competitive Strategy Innovation and Leadership Award

The Frost & Sullivan Best Practices Awards recognise companies in a variety of regional and global...
Sponsored by

Three Tips to Improve Safety in the Oil Field

Working oil fields will always be tough work with inherent risks. There’s no getting around that. Ther...
Sponsored by

Pipeline Integrity: Best Practices to Prevent, Detect, and Mitigate Commodity Releases

Commodity releases can have catastrophic consequences, so ensuring pipeline integrity is crucial for p...
Sponsored by

AVEVA’s Digital Asset Approach - Defining a new era of collaboration in capital projects and asset operations

There is constant, intensive change in the capital projects and asset life cycle management. New chall...
Sponsored by

Transforming the Oil and Gas Industry with EPPM

With budgets in the billions, timelines spanning years, and life cycles extending over decades, oil an...
Sponsored by

Asset Decommissioning in Oil & Gas: Transforming Business

Asset intensive organizations like Oil and Gas have their own industry specific challenges when it com...
Sponsored by

Squeezing the Green: How to Cut Petroleum Downstream Costs and Optimize Processing Efficiencies with Enterprise Project Portfolio Management Solutions

As the downstream petroleum industry grapples with change in every sector and at every level, includin...
Sponsored by

7 Steps to Improve Oil & Gas Asset Decommissioning

Global competition and volatile markets are creating a challenging business climate for project based ...
Sponsored by
Available Webcasts

On Demand

OGJ's Midyear Forecast 2015

Fri, Jul 10, 2015

This webcast is to be presented by OGJ Editor Bob Tippee and Senior Economic Editor Conglin Xu.  They will summarize the Midyear Forecast projections in key categories, note important changes from January’s forecasts, and examine reasons for the adjustments.

register:WEBCAST


Predictive Analytics in your digital oilfield - Optimize Production Yield and Reduce Operational Costs

Tue, Jul 7, 2015

Putting predictive analytics to work in your oilfield can help you anticipate failures, plan and schedule work in advance, eliminate emergency work and catastrophic failures, and at the same time you can optimize working capital and improve resource utilization.  When you apply analytic capabilities to critical production assets it is possible to reduce non-productive time and increase your yield.

Learn how IBM's analytics capabilities can be applied to critical production assets with the goal of reducing non-productive time, increasing yield and reducing operations costs.

register:WEBCAST


Cognitive Solutions for Upstream Oil and Gas

Fri, Jun 12, 2015

The oil & gas sector is under pressure on all sides. Reserves are limited and it’s becoming increasingly expensive to find and extract new resources. Margins are already being squeezed in an industry where one wrong decision can cost millions. Analyzing data used in energy exploration can save millions of dollars as we develop ways to predict where and how to extract the world’s massive energy reserves.

This session with IBM Subject Matter Experts will discuss how IBM Cognitive Solutions contribute to the oil and gas industry using predictive analytics and cognitive computing, as well as real time streaming for exploration and drilling.

register:WEBCAST


The Alternative Fuel Movement: Four Need-to-Know Excise Tax Complexities

Thu, Jun 4, 2015

Discussion on how to approach, and ultimately embrace, the alternative fuel market by pulling back the veil on excise tax complexities. Taxes may be an aggravating part of daily operations, but their accuracy is crucial in your path towards business success.

register:WEBCAST


Emerson Micro Motion Videos

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected