HOUSTON, May 7 -- Petroleo Brasiliero SA (Petrobras) Monday claimed a world record in ultradeep waters for the installation of a subsea natural gas lift manifold at a depth of 1,885 m (6,184 ft.) in Roncador field in the Campos basin off Brazil.

Speaking at the Offshore Technology Conference, Petrobras Pres. and CEO Francisco Gros said the installation was unique for subsea equipment at this depth because of its size and weight: 10 x 7.5 x 4 m (32.8 x 24.6 x 13.1 ft.) and 191 tons (including installation equipment).

This marked the first time the installation of such heavy equipment surpassed waters deeper than 1,000 m. The manifold was installed with steel cables and support vessels. It was designed to reduce gas lift costs by distributing gas coming from the production unit via a single gas line for injection into six wells, Petrobras said.

The manifold is scheduled to go on stream by Dec. 31 following the interconnection of the wells to the manifold and the manifold to the Brasil floating production storage and offloading vessel.

The installation was carried out jointly by the Amethyst-1 (SS-47) semisubmersible drilling rig and the Asso 23 anchor-handling supply tug, as well as various supply boats.

The manifold was loaded on the deck of the Amethyst-1 and lowered into 90 m of waterwith the semi's lateral crane. Beyond that depth, the weight of the manifold was transferred to a 4-in. cable that was connected simultaneously to the Asso 23 tug winch and the semi's drilling tower.

With the objective of minimizing dynamic amplification, when lowered to the 900-m depth, the rig compensator and the riser tensioners were activated. The manifold was placed on the seabed only 2.3 m from the target location.

Aside from the cost savings of $4 million, the installation method also freed for service the the SS-51 semisubmersible that was originally scheduled for manifold installation, Petrobras said. The SS-51 is rated to work in 2,000 m of water, while the Amethyst-1 is rated to work in only 1,000 m.

Deepwater records
Over the past 15 years, Petrobras has set a series of deepwater records in the Campos basin, including the world record set 2 years ago for deepwater oil production, 1,853 m (6,079 ft) in Roncador field. Although the well has since been shut in, the record has yet to be surpassed.

Meanwhile, Petrobras already has wells completed in waters up to 1,886 m (6,187 ft) deep that are waiting to be brought on stream.

Related Articles

BHI: US rig count down 87 units in 10th straight week of losses

02/06/2015 The US drilling rig count plunged 87 units, a decline that was again spurred mostly by oil rigs, to settle at 1,456 rigs working during the week en...

Oil-price collapse may aggravate producing nations’ other problems

02/05/2015 The recent global crude-oil price plunge could be aggravating underlying problems in Mexico, Colombia, and other Western Hemisphere producing natio...

North Reggane gas project development drilling starts in Algeria

02/05/2015

The North Reggane consortium has started development drilling at its gas project in the Algerian Sahara.

Oil production begins at Nasr Phase-1 offshore Abu Dhabi

02/05/2015 The first phase of Nasr oil field offshore Abu Dhabi will be producing 22,000 b/d by yearend, according to United Arab Emirates news agency WAM.

Woodside lets FEED contract for Greater Western Flank project

02/05/2015 Woodside Petroleum Ltd. has let a contract to Wood Group Kenny for the front-end engineering and design for the flowline system and associated proc...

Deloitte studies oil supply growth for 2015-16

02/04/2015 A Deloitte MarketPoint analysis suggested large-field projects, each producing more than 25,000 b/d, could bring on 1.835 million b/d in oil supply...

Inpex starts development drilling at Ichthys field

02/04/2015

Inpex Corp. has started development drilling in Ichthys gas-condensate field in the Browse basin, about 200 km offshore Western Australia.

BG’s 2015 budget ‘significantly lower than 2014’

02/03/2015 BG Group plans capital expenditures on a cash basis of $6-7 billion in 2015, a range it says is “significantly lower than 2014” due to “a lower oil...

BP trims capital budget by $4-6 billion

02/03/2015 BP PLC plans an organic capital expenditure of $20 billion in 2015, down from the previous guidance $24-26 billion. Total organic capital expenditu...
White Papers

AVEVA’s Digital Asset Approach - Defining a new era of collaboration in capital projects and asset operations

There is constant, intensive change in the capital projects and asset life cycle management. New chall...
Sponsored by

Transforming the Oil and Gas Industry with EPPM

With budgets in the billions, timelines spanning years, and life cycles extending over decades, oil an...
Sponsored by

Asset Decommissioning in Oil & Gas: Transforming Business

Asset intensive organizations like Oil and Gas have their own industry specific challenges when it com...
Sponsored by

Squeezing the Green: How to Cut Petroleum Downstream Costs and Optimize Processing Efficiencies with Enterprise Project Portfolio Management Solutions

As the downstream petroleum industry grapples with change in every sector and at every level, includin...
Sponsored by

7 Steps to Improve Oil & Gas Asset Decommissioning

Global competition and volatile markets are creating a challenging business climate for project based ...
Sponsored by

The impact of aging infrastructure in process manufacturing industries

Process manufacturing companies in the oil and gas, utilities, chemicals and natural resource industri...
Sponsored by

What is System Level Thermo-Fluid Analysis?

This paper will explain some of the fundamentals of System Level Thermo-Fluid Analysis and demonstrate...

Accurate Thermo-Fluid Simulation in Real Time Environments

The crux of any task undertaken in System Level Thermo-Fluid Analysis is striking a balance between ti...
Available Webcasts


Prevention, Detection and Mitigation of pipeline leaks in the modern world

When Thu, Apr 30, 2015

Preventing, detecting and mitigating leaks or commodity releases from pipelines are a top priority for all pipeline companies. This presentation will look at various aspects related to preventing, detecting and mitigating pipeline commodity releases from a generic and conceptual point of view, while at the same time look at the variety of offerings available from Schneider Electric to meet some of the requirements associated with pipeline integrity management. 

register:WEBCAST



On Demand

Global LNG: Adjusting to New Realities

Fri, Mar 20, 2015

Oil & Gas Journal’s March 20, 2015, webcast will look at how global LNG trade will be affected over the next 12-24 months by falling crude oil prices and changing patterns and pressures of demand. Will US LNG production play a role in balancing markets? Or will it add to a growing global oversupply of LNG for markets remote from easier natural gas supply? Will new buyers with marginal credit, smaller requirements, or great need for flexibility begin to look attractive to suppliers? How will high-cost, mega-projects in Australia respond to new construction cost trends?

register:WEBCAST


US Midstream at a Crossroads

Fri, Mar 6, 2015

Oil & Gas Journal’s Mar. 6, 2015, webcast will focus on US midstream companies at an inflection point in their development in response to more than 6 years shale oil and gas production growth. Major infrastructure—gas plants, gathering systems, and takeaway pipelines—have been built. Major fractionation hubs have expanded. Given the radically changed pricing environment since mid-2014, where do processors go from here? What is the fate of large projects caught in mid-development? How to producers and processors cooperate to ensure a sustainable and profitable future? This event will serve to set the discussion table for the annual GPA Convention in San Antonio, Apr. 13-16, 2015.

This event is sponsored by Leidos Engineering.

register:WEBCAST


The Future of US Refining

Fri, Feb 6, 2015

Oil & Gas Journal’s Feb. 6, 2015, webcast will focus on the future of US refining as various forces this year conspire to pull the industry in different directions. Lower oil prices generally reduce feedstock costs, but they have also lowered refiners’ returns, as 2015 begins with refined products priced at lows not seen in years. If lower per-barrel crude prices dampen production of lighter crudes among shale plays, what will happen to refiners’ plans to export more barrels of lighter crudes? And as always, refiners will be affected by government regulations, particularly those that suppress demand, increase costs, or limit access to markets or supply.

register:WEBCAST


Emerson Micro Motion Videos

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected