Model process could speed up pipeline permitting, working group says


By the OGJ Online Staff


HOUSTON, Sept. 5 -- States should consider developing a model process for siting natural gas pipelines, a working group of state utility regulators and elected officials said, to help speed up the permitting process.

Many industry participants have pointed to a prospective shortfall in pipeline capacity as limiting its ability to serve a projected rise in gas demand. The existing gas infrastructure was not planned to meet the expected rate of gas consumption growth which the nation will experience in the next decade, particularly demand driven by electric power generation, the working group said.

Barriers to expansion include duplication at several levels of government, concluded the group, which included representatives from the National Association of Regulatory Utility Commissioners, the Interstate Oil and Gas Compact Commission, the Department of Energy, the Federal Energy Regulatory Commission, the Department of Interior, the American Gas Association (AGA), and the Interstate Natural Gas Association of America.

As a result of recent events, "new and expanding businesses often no longer assume needed energy supplies will be available," the report concluded. To expand, or develop new businesses, as well as meet basic human needs of the population, it said states must ensure that an adequate energy infrastructure is available.

The National Petroleum Council estimated more than 38,000 miles of new gas transmission lines will be needed, as well as 263,000 miles of new distribution lines. The working group said that much pipeline will require the attention of every state, and many regulatory bodies within the states.

State and local regulations add oversight critical to the unique interests of the state or locality, the working group conceded. However, it said only a few states effectively coordinate the natural gas pipeline permitting process, while often overlapping federal, state, and local regulatory requirements can add many months -- and sometimes years -- to building a pipeline.

"Consumers won't get to enjoy the benefits of natural gas, such as cleaner air, more jobs at home, and increased energy efficiency, if they can't get the gas delivered to them," said David N. Parker, CEO of the AGA.

To speed up pipeline construction, the working group recommended a series of changes, including:

-- Governors should establish within the office of governor a coordinating effort to eliminate duplication among state and local natural gas permitting entities. The coordinating effort will insure all data needed are provided by the applicant in a timely fashion and will facilitate sharing of information and experts among state and federal agencies, and with local governments.

-- States should decide, prior to beginning a natural gas pipeline siting process, what information they need to collect and communicate that information to the general public and to the pipeline. States should identify all participants in the permitting process and coordinate regulatory roles, with the goal of processing information only once. States should consider naming a lead agency which would have the authority to monitor processing schedules within existing regulatory requirements.

-- Every state economic development office (Commerce Department) should be involved with the coordination effort and recommend actions to streamline the process.

-- States should work with the federal government to conduct regional needs and pipeline/utility corridor identification. This federal-state coordination is endorsed in Executive Order 13212, issued May 18, in which President Bush created a federal interagency task force charged with "...setting up appropriate mechanisms to coordinate federal, state, tribal, and local permitting in geographic areas where increased permitting activity is expected."

-- States should consider instituting a task force of state environmental experts to focus and coordinate all environmental issues stemming from the proposed pipeline. When time-sensitive issues arise, the governors need a plan for reaction, which would be coordinated with federal entities where appropriate.

-- States should encourage research spending, including government, university, and pipeline spending, to develop pipeline installation techniques that disturb less surface, complete the installation more quickly, and enhance safety.

-- States should review policies, procedures, and regulations for the siting and installation of natural gas pipelines to eliminate duplication, reduce the cost and time of review, without compromising state regulatory oversight.

-- States should be a partner in FERC pipeline prefiling citizen meetings, and consider developing similar citizen meetings for intrastate projects.

-- States should encourage public education and outreach on the part of the pipeline. Such public education should include adequate information about steps taken to ensure public safety, details of construction, and contingency plans.

-- States should consider developing a model for clear and accessible state and local regulations governing the siting of natural gas pipelines.

Related Articles

Woodside lets contracts for Browse LNG project

07/06/2015 Woodside Petroleum Ltd. has let more contracts for the Browse floating LNG project offshore Western Australia. The contracts, awarded to a Technip-...

Emerging producers offered guidelines for governance

07/06/2015 Like most worthy endeavors, governing oil and gas activity at the national level is easier said than done-especially where oil and gas never before...

Nelson-Farrar Quarterly Costimating Indexes for selected equipment items

07/06/2015 The Nelson-Farrar refinery construction index rose to 2,475.6 by December 2012 from 2,467.4 in January of the same year. The index continued to ris...

The price of oil and OPEC-history repeating?

07/06/2015 The world oil market today is characterized by a standoff between the Organization of Petroleum Exporting Countries (OPEC) and non-OPEC producers a...

Oman lets contract for Sohar refinery unit revamp

07/06/2015 Oman Oil Refineries & Petroleum Industries Co., has let a contract to MAN Diesel & Turbo SE, Augsburg, Germany, for work related to the ove...

US House committee leaders send letters to Plains, PHMSA about leak

07/06/2015 US House Energy and Commerce Committee leaders from both parties asked Plains Pipeline LP and the US Pipeline and Hazardous Materials Safety Admini...

Gas faces more competition from coal, renewables, IEA official says

07/06/2015 Natural gas faces growing competition from coal and renewable energy sources at a time when its potential demand growth is slowing down, an Interna...

Total unveils development sites for renamed Papua LNG project

07/06/2015 Total SA and its joint venture partners Oil Search Ltd. and InterOil have announced key infrastructure sites for development of the proposed Elk-An...

Global oil glut continues despite increasing demand

07/06/2015 A year since crude prices plunged, oversupply lingers, evident in a record-setting stock build, as production by members of the Organization of Pet...
White Papers

2015 Global Engineering Information Management Solutions Competitive Strategy Innovation and Leadership Award

The Frost & Sullivan Best Practices Awards recognise companies in a variety of regional and global...
Sponsored by

Three Tips to Improve Safety in the Oil Field

Working oil fields will always be tough work with inherent risks. There’s no getting around that. Ther...
Sponsored by

Pipeline Integrity: Best Practices to Prevent, Detect, and Mitigate Commodity Releases

Commodity releases can have catastrophic consequences, so ensuring pipeline integrity is crucial for p...
Sponsored by

AVEVA’s Digital Asset Approach - Defining a new era of collaboration in capital projects and asset operations

There is constant, intensive change in the capital projects and asset life cycle management. New chall...
Sponsored by

Transforming the Oil and Gas Industry with EPPM

With budgets in the billions, timelines spanning years, and life cycles extending over decades, oil an...
Sponsored by

Asset Decommissioning in Oil & Gas: Transforming Business

Asset intensive organizations like Oil and Gas have their own industry specific challenges when it com...
Sponsored by

Squeezing the Green: How to Cut Petroleum Downstream Costs and Optimize Processing Efficiencies with Enterprise Project Portfolio Management Solutions

As the downstream petroleum industry grapples with change in every sector and at every level, includin...
Sponsored by

7 Steps to Improve Oil & Gas Asset Decommissioning

Global competition and volatile markets are creating a challenging business climate for project based ...
Sponsored by
Available Webcasts

On Demand

OGJ's Midyear Forecast 2015

Fri, Jul 10, 2015

This webcast is to be presented by OGJ Editor Bob Tippee and Senior Economic Editor Conglin Xu.  They will summarize the Midyear Forecast projections in key categories, note important changes from January’s forecasts, and examine reasons for the adjustments.

register:WEBCAST


Predictive Analytics in your digital oilfield - Optimize Production Yield and Reduce Operational Costs

Tue, Jul 7, 2015

Putting predictive analytics to work in your oilfield can help you anticipate failures, plan and schedule work in advance, eliminate emergency work and catastrophic failures, and at the same time you can optimize working capital and improve resource utilization.  When you apply analytic capabilities to critical production assets it is possible to reduce non-productive time and increase your yield.

Learn how IBM's analytics capabilities can be applied to critical production assets with the goal of reducing non-productive time, increasing yield and reducing operations costs.

register:WEBCAST


Cognitive Solutions for Upstream Oil and Gas

Fri, Jun 12, 2015

The oil & gas sector is under pressure on all sides. Reserves are limited and it’s becoming increasingly expensive to find and extract new resources. Margins are already being squeezed in an industry where one wrong decision can cost millions. Analyzing data used in energy exploration can save millions of dollars as we develop ways to predict where and how to extract the world’s massive energy reserves.

This session with IBM Subject Matter Experts will discuss how IBM Cognitive Solutions contribute to the oil and gas industry using predictive analytics and cognitive computing, as well as real time streaming for exploration and drilling.

register:WEBCAST


The Alternative Fuel Movement: Four Need-to-Know Excise Tax Complexities

Thu, Jun 4, 2015

Discussion on how to approach, and ultimately embrace, the alternative fuel market by pulling back the veil on excise tax complexities. Taxes may be an aggravating part of daily operations, but their accuracy is crucial in your path towards business success.

register:WEBCAST


Emerson Micro Motion Videos

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected