Thailand's Egat trims capital spending plans


By an OGJ Online Correspondent

BANGKOK, May 8 -- The Electricity Generating Authority of Thailand (Egat) will cut capital outlays almost 15% between 2003-2006 under revisions to its long-term investment plan.

Capital spending in the period would be trimmed to 144 billion baht ($3.18 billion US) from 170 billion baht, said senior officials of the Thai state power utility which controls 75% of the country's combined installed capacity.

The 14.79% reduction is largely in line with Egat's new directive to narrow the kingdom's total generating reserves to no less than 15% above domestic demand. The reserve margin had been set at 25%.

The new policy is also meant to support the Thaksin Shinawatra Administration's goal of reducing costly imports of capital goods. State enterprises, including Egat, are among the largest foreign exchange losers.

Egat officials pointed out that the amount of procurement of import content in the 2003-2006 could be cut by 3.5 billion baht, representing 4.99% of total capital outlay planned in the period.

For 2003, the proposed reduction is 1.6 billion baht; 3.9 billion baht for 2004; 7 billion baht for 2005; and 12.5 billion baht for 2006.

Egat said it will immediately curtail capital outlays for 2001 and 2002 by 1.7 billion baht. As a result, its investment for 2001 drops by 1.2 billion baht to 28 billion baht, or a 4.11% cut. The projects that will be most immediately affected in 2001 are construction of the Surat Thani power plant and installation of flue gas desulfurization equipment at Units 4-7 of the lignite-fired Mae Moh power complex. Payment will be postponed to 2002.

For 2002, Egat sources said cuts will be in the magnitude of 478 million baht, reducing the investment for the year to 20.8 billion baht. The cutback , aimed at import content, will have the most bearing on the Surat Thani power plant project and the ninth phase transmission line expansion scheme.

The Petroleum Authority of Thailand already said the reduction policy may force a delay in a 3 billion baht gas pipeline project to serve the Surat Thani power project. The 20-in., 80-km transmission line was originally set to come onstream in 2003 with a gas throughput capacity of 150 MMcfd.

Related Articles

Williams, DCP start gas flow from Keathley Canyon Connector

02/10/2015 Williams, through its general partner ownership of Williams Partners, and DCP Midstream Partners LP have started operations from their newly extend...

Senators’ bill aims to curb flaring by expediting permit process

02/09/2015 North Dakota and Wyoming’s US senators introduced legislation that aims to capture methane and reduce flaring by expediting procedures for obtainin...

MOL, Transpetrol complete Hungary-Slovakia crude line expansion

02/09/2015 MOL Group and Transpetrol AS finished reconstruction and capacity expansion of the Friendship I-Adria oil pipeline leg between Szazhalombatta, Hung...

NCOC lets $1.8-billion pipeline contract for Kashagan field

02/06/2015 North Caspian Operating Co. (NCOC) has let a $1.8-billion engineering and construction contract to ERSAI Caspian Contractor LLC, a subsidiary of Sa...

AOPL releases 2015 safety performance and strategic planning report

02/06/2015 The Association of Oil Pipe Lines is committed to further improvements despite a 99.99% safe petroleum liquids delivery rate, AOPL Pres. and Chief ...

PAA to expand Delaware basin crude pipeline systems

02/05/2015 Plains All American Pipeline LP (PAA) plans to build two Delaware basin crude oil pipelines and related gathering systems, to expand its existing B...

Alberta’s premier seeks more North American energy integration

02/05/2015 Better policy integration and cooperation will be needed for Canada, Mexico, and the US to fully realize the North American energy renaissance’s po...

Oil, gas infrastructure investments essential, House panel told

02/04/2015 Investments in oil and gas transportation and storage should move ahead because they are essential in continuing the US economic recovery and North...

EPA suggests DOS reconsider Keystone XL climate impact conclusions

02/03/2015 The US Department of State might want to reconsider its conclusions regarding potential climate impacts from the proposed Keystone XL crude oil pip...
White Papers

Transforming the Oil and Gas Industry with EPPM

With budgets in the billions, timelines spanning years, and life cycles extending over decades, oil an...
Sponsored by

Asset Decommissioning in Oil & Gas: Transforming Business

Asset intensive organizations like Oil and Gas have their own industry specific challenges when it com...
Sponsored by

Squeezing the Green: How to Cut Petroleum Downstream Costs and Optimize Processing Efficiencies with Enterprise Project Portfolio Management Solutions

As the downstream petroleum industry grapples with change in every sector and at every level, includin...
Sponsored by

7 Steps to Improve Oil & Gas Asset Decommissioning

Global competition and volatile markets are creating a challenging business climate for project based ...
Sponsored by

The impact of aging infrastructure in process manufacturing industries

Process manufacturing companies in the oil and gas, utilities, chemicals and natural resource industri...
Sponsored by

What is System Level Thermo-Fluid Analysis?

This paper will explain some of the fundamentals of System Level Thermo-Fluid Analysis and demonstrate...

Accurate Thermo-Fluid Simulation in Real Time Environments

The crux of any task undertaken in System Level Thermo-Fluid Analysis is striking a balance between ti...

6 ways for Energy, Chemical and Oil and Gas Companies to Avert the Impending Workforce Crisis

As many as half of the skilled workers in energy, chemical and oil & gas industries are quickly he...
Sponsored by
Available Webcasts

On Demand

Global LNG: Adjusting to New Realities

Fri, Mar 20, 2015

Oil & Gas Journal’s March 20, 2015, webcast will look at how global LNG trade will be affected over the next 12-24 months by falling crude oil prices and changing patterns and pressures of demand. Will US LNG production play a role in balancing markets? Or will it add to a growing global oversupply of LNG for markets remote from easier natural gas supply? Will new buyers with marginal credit, smaller requirements, or great need for flexibility begin to look attractive to suppliers? How will high-cost, mega-projects in Australia respond to new construction cost trends?

register:WEBCAST


US Midstream at a Crossroads

Fri, Mar 6, 2015

Oil & Gas Journal’s Mar. 6, 2015, webcast will focus on US midstream companies at an inflection point in their development in response to more than 6 years shale oil and gas production growth. Major infrastructure—gas plants, gathering systems, and takeaway pipelines—have been built. Major fractionation hubs have expanded. Given the radically changed pricing environment since mid-2014, where do processors go from here? What is the fate of large projects caught in mid-development? How to producers and processors cooperate to ensure a sustainable and profitable future? This event will serve to set the discussion table for the annual GPA Convention in San Antonio, Apr. 13-16, 2015.

This event is sponsored by Leidos Engineering.

register:WEBCAST


The Future of US Refining

Fri, Feb 6, 2015

Oil & Gas Journal’s Feb. 6, 2015, webcast will focus on the future of US refining as various forces this year conspire to pull the industry in different directions. Lower oil prices generally reduce feedstock costs, but they have also lowered refiners’ returns, as 2015 begins with refined products priced at lows not seen in years. If lower per-barrel crude prices dampen production of lighter crudes among shale plays, what will happen to refiners’ plans to export more barrels of lighter crudes? And as always, refiners will be affected by government regulations, particularly those that suppress demand, increase costs, or limit access to markets or supply.

register:WEBCAST


Oil & Gas Journal’s Forecast & Review/Worldwide Pipeline Construction 2015

Fri, Jan 30, 2015

The  Forecast & Review/Worldwide Pipeline Construction 2015 Webcast will address Oil & Gas Journal’s outlooks for the oil market and pipeline construction in a year of turbulence. Based on two annual special reports, the webcast will be presented by OGJ Editor Bob Tippee and OGJ Managing Editor-Technology Chris Smith.
The Forecast & Review portion of the webcast will identify forces underlying the collapse in crude oil prices and assess prospects for changes essential to recovery—all in the context of geopolitical pressures buffeting the market.

register:WEBCAST


Emerson Micro Motion Videos

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected