Canada's Terra Nova field to get ice-resistant FPSO this fall


By Judy Clark
Associate Editor
Oil and Gas Journal

HOUSTON, May 1 -- The first floating production, storage, and offloading (FPSO) vessel to operate in North American waters is scheduled to start production at Terra Nova field off Newfoundland this fall.

The field, in the Jeanne d'Arc basin 325 km southeast of St. John's, is one of 15 "significant" oil discoveries in the basin, the largest of which is Hibernia -- in production since1997.

"Hibernia and Terra Nova are the largest conventional oil pools found in Canada since the 1960s," said Gary Bruce, vice-president of offshore development and operations for Terra Nova operator Petro-Canada. Bruce described the Terra Nova project Monday at the Offshore Technology Conference in Houston.

He said that four fields dominate the basin. Hibernia has reserves of more than 700 million bbl, Terra Nova 400 million bbl, White Rose 200-250 million bbl, and Hebron-Ben Nevis, 600-700 million bbl -- half of which is heavy oil at about 22°-gravity.

"We have some interesting challenges," Bruce said.

When the four fields come on stream and the smaller fields are tied into them, the basin could produce 300,000 b/d over the next 25 years.

"The [Terra Nova] FPSO contains all topside oil production and processing equipment, as well as storage capacity for 960,000 bbl of oil," Bruce said.

"While there are nearly 70 FPSOs in service or under development in the world, the Terra Nova FPSO will be the first of its kind developed for the unique environmental conditions offshore Newfoundland, " he said.

The vessel has an exceptionally tough double hull and 3,000 tonnes of extra ice-strengthening steel to withstand contact with sea ice (mid-February-April) and icebergs (February-July), including any "unacceptable" iceberg of 100,000 tonnes.

As many as 600 icebergs break off the coast of Greenland each year and float southward on the Labrador current toward the Grand Banks, according to R. B. Dugal of Petro-Canada Oil & Gas.

He spoke at a separate OTC technical session on ice detection and management in Terra Nova. Workboats successfully deflect about 97% of the icebergs. Despite the intensive ice detection and management effort, in April 2000 there were 10 icebergs near the production areas, one within a half mile of Hibernia wells and one within a quarter mile of the Terra Nova wellheads.

Because iceberg scour is such a threat to facilities in this environment, all flowlines are buried under the seabed for protection, insulation, and stability, and wellheads in Terra Nova field are 10-12 ft lower than the seabed in "glory holes" dredged by trailer suction. The holes are 210 ft long by 80 ft wide by 30 ft deep.

Bruce said the Terra Nova FPSO is designed to stay anchored during a 100-year storm with 90-ft waves, withstand the impact of a 100,000-tonne iceberg, and, in less than 20 minutes, get out of the way of icebergs of about 2 million tonnes.

The FPSO is 958 ft long, 149 ft in breadth, and has a draft of 92 ft. Its operating draft is 42-61 ft. Maximum displacement at operating draught is 194,000 tonnes.

It reportedly has the largest disconnectable turret ever built, weighing 3,000 tonnes, standing 210 ft high, and having 19 risers attached. The turret is connected to a spider buoy, which has risers and anchor chains attached. When the FPSO moves off location, the spider buoy is released, using automated controls. It then floats some 130 ft below sea level until the FPSO returns to hook onto it and pull it into the turret for rejoining.

Petro-Canada operates Terra Nova on behalf of its partners ExxonMobil Corp., Husky Oil Operations Ltd., Norsk Hydro Canada Oil & Gas Inc., Murphy Oil Co. Ltd., Mosbacher Operating Ltd., and Chevron Corp. affiliate Chevron Canada Resources.

The FPSO is at Bull Arm, Newf., in the latter stages of hookup and commissioning. It has been docked there since May 2000 when it arrived from the Daewoo Corp. shipyard in South Korea where it was built. The project schedule calls for first oil by yearend.

Delays have increased costs by 35% since the project was sanctioned. Operating costs in Hibernia, however, are falling and are now at less than $1.50/bbl. "We expect a similar cost at Terra Nova during peak production years," Bruce said.

First phase of Terra Nova production calls for 24 wells -- 14 producers, 7 water injectors, and 3 gas injectors.

Meanwhile, the semisubmersible Henry Goodrich already has drilled the six wells needed for startup.

The Newfoundland offshore area is vast -- 225,000 sq miles -- and Petro-Canada believes that the Flemish Pass basin, in more than 3,000 ft of water, may contain the next large oil field. It lies in deeper water, at over 3,000 ft. Partners Norsk Hydro, ExxonMobil, and Chevron contracted a 1,500-sq mile 3D seismic program last year and are evaluating results.

Although a pipeline to produce offshore Newfoundland gas is not currently economically feasible and faces the technological challenge of iceberg conditions, the government is assessing potential routes for a $2.5 billion (Can.), 36-in., 1 bcfd line.

Related Articles

Canada Briefs

12/12/2014

Chevron, ONGC among companies awarded 15 exploration permits by New Zealand

12/09/2014 New Zealand’s government has awarded six onshore permits across the Taranaki, West Coast, and East Coast basins, and nine offshore permits across t...

CSB releases final report on Chevron Richmond refinery fire

11/17/2014 The US Chemical Safety Board (CSB) has issued the final regulatory report on its investigation of the August 2012 pipe rupture and ensuing fire at ...

Hess to develop deepwater gulf oil field

10/29/2014 Production is to begin in 2018 from deepwater Stampede oil field in the Gulf of Mexico under a development plan approved by operator Hess Corp. and...

NGSA forecasts lower winter gas prices on a combined analysis

10/13/2014 In its 14th annual Winter Outlook assessment of the natural gas market, the Natural Gas Supply Association (NGSA) expects downward price pressure o...

Chevron Canada to sell 30% in Duvernay shale to Kufpec Canada for $1.5 billion

10/06/2014 Chevron Corp. said its Chevron Canada Ltd. unit plans to sell a 30% interest in its Duvernay shale play to Kuwait Foreign Petroleum Exploration Co....

Bahamas: Gravity data suggest existence of Triassic-Jurassic syn-rift

10/06/2014 Recent analyses of gravity, magnetic, and seismic data in the southeastern region of the Bahamas provide clear evidence for the presence of a salt ...

EnLink Midstream to purchase Gulf Coast gas pipeline systems

09/29/2014 A subsidiary of EnLink Midstream Partners LP and EnLink Midstream LLC has agreed to acquire Gulf Coast natural gas pipeline assets, including the B...

Western gulf lease sale attracts $110 million in high bids

08/20/2014 Gulf of Mexico western planning area Lease Sale 238 drew 93 bids from 14 companies over 81 blocks covering 433,823 acres, totaling $109,951,644 in ...

White Papers

AVEVA NET Accesses and Manages the Digital Asset

Global demand for new process plants, power plants and infrastructure is increasing steadily with the ...
Sponsored by

AVEVA’s Approach for the Digital Asset

To meet the requirements for leaner project execution and more efficient operations while transferring...
Sponsored by

Diversification - the technology aspects

In tough times, businesses seek to diversify into adjacent markets or to apply their skills and resour...
Sponsored by

Engineering & Design for Lean Construction

Modern marketing rhetoric claims that, in order to cut out expensive costs and reduce risks during the...
Sponsored by

Object Lessons - Why control of engineering design at the object level is essential for efficient project execution

Whatever the task, there is usually only one way to do it right and many more to do it wrong. In the c...
Sponsored by

Plant Design for Lean Construction - at your fingertips

One area which can provide improvements to the adoption of Lean principles is the application of mobil...
Sponsored by

How to Keep Your Mud System Vibrator Hose from Getting Hammered to Death

To prevent the vibrating hoses on your oilfield mud circulation systems from failing, you must examine...
Sponsored by

Duty of Care

Good corporate social responsibility means implementing effective workplace health and safety measures...
Sponsored by

Available Webcasts


On Demand

Optimizing your asset management practices to mitigate the effects of a down market

Thu, Dec 11, 2014

The oil and gas market is in constant flux, and as the price of BOE (Barrel of Oil Equivalent) goes down it is increasingly important to optimize your asset management strategy to stay afloat.  Attend this webinar to learn how developing a solid asset management plan can help your company mitigate costs in any market.

register:WEBCAST


Parylene Conformal Coatings for the Oil & Gas Industry

Thu, Nov 20, 2014

In this concise 30-minute webinar, participants have an opportunity to learn more about how Parylene coatings are applied, their features, and the value they add to devices and components.

register:WEBCAST


Utilizing Predictive Analytics to Optimize Productivity in Oil & Gas Operations

Tue, Nov 18, 2014

Join IBM on Tuesday, November 18 @ 1pm CST to explore how Predictive Analytics can help your organization maximize productivity, operational performance & associated processes to drive enterprise wide productivity and profitability.

register:WEBCAST


US HYDROCARBON EXPORTS Part 3 — LNG

Fri, Nov 14, 2014

US LNG Exports, the third in a trilogy of webcasts focusing on the broad topic of US Hydrocarbon Exports.

A discussion of the problems and potential for the export of US-produced liquefied natural gas.

These and other topics will be discussed, with the latest thoughts on U.S. LNG export policy.

register:WEBCAST


Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected