'Unprecedented' safety requirements add millions and months to pipeline project


Sam Fletcher
OGJ Online

It will take Longhorn Partners Pipeline LP another 6 months to implement additional safety features that will add millions to the cost of a $399 million pipeline project, began in 1995, to carry refined products across Texas from Houston to El Paso, a spokesman for that limited partnership said Tuesday.

US Environmental Protection Agency officials Monday approved an "unprecedented" safety and mitigation program that brings that project a giant step closer to completion. That move came on instructions from US President Bill Clinton's top aides on the White House Council on Environmental Quality in September after Longhorn Partners agreed to 40 steps to reduce ecological dangers along the pipeline route.

Included are "extraordinary safety and mitigation measures that have not been required on any pipeline in the country" and which meet or exceed any future pipeline safety requirements under consideration in congress, said government officials.

The pipeline will be the first to ban products that contain methyl tertiary butyl ether or similar additives�tertiary amyl methyl ether, ethyl tertiary butyl ether, di-isopropyl ether�in greater than trace amounts, EPA officials said.

The 700-mile pipeline includes a 450-mile section from Houston to Crane in the Permian Basin that was built in the 1950s to carry West Texas crude to Gulf Coast refineries. Longhorn Partners acquired that pipeline in 1995, with the aim of reversing its flow to carry gasoline and other refined products from Houston-area refineries to markets in West Texas, New Mexico, and Arizona.

That original pipeline crosses the environmentally sensitive Edwards Aquifer in central Texas, an unique groundwater system that includes one of the most prolific artesian aquifers on the globe. It is officially designated as the sole source of drinking water for some 1.5 million people, including the cities of San Antonio and Austin, the Texas capital.

Protection, observation measures
As part of the environmental agreement, Longhorn Partners will replace 19 miles of 1950s-vintage pipe over a section of the Edwards Aquifer near Austin with thicker-walled pipe. The replacement pipe is to be buried at a depth to reduce the potential for third-party damage, with a concrete barrier installed over it as additional protection.

The partners also are required to design and develop a trench across that section of the aquifer's recharge and contributing zones to capture any accidental release. They also must install a system across the recharge and nearby contributing zones that is capable of detecting "even very small leaks" within 12-20 minutes of initial discharge.

Pipeline pump stations are to be inspected every 2 1/2 days in environmentally sensitive and highly populated areas. Remote cameras are to be installed to monitor all pump stations prior to start up.

Longhorn Partners formed an accident response partnership with Boots & Coots International Well Control Inc. of Houston to ensure quick response to any emergency. Pipeline officials said they will fund an office for Boots & Coots in Central Texas that, in addition to the emergency firm's existing oil field facilities on the Gulf Coast and in the Permian Basin, will assure prompt reaction at any point along the pipeline.

Moreover, new valves are being installed on the pipeline in sensitive areas like the Edwards Aquifer and river crossings that will let operators quickly shut down the flow of products through the pipeline and safely drain the line if necessary. "We had already installed some of those valves and are adding more as a result of the study," said Michael Patterson, partnership spokesman.

Under the environmental agreement, Longhorn must perform semiannual pipe-to-soil potential surveys in sensitive areas along the pipeline�twice as often as currently required by Department of Transportation regulations, officials said.

The partnership also must do aerial and ground surveillance of the pipeline every day in the Edwards Aquifer area; every 2 1/2 days in other environmentally sensitive and highly populated areas; and weekly in all other regions. All of those schedules also are more frequent than now required by law, officials said.

Pipeline marker signs in both English and Spanish must be posted at more frequent intervals along the pipeline route than now specified by industry standards, including at all above-ground facilities and on each side of public road, water and railroad crossings.

In addition, Longhorn Pipeline is required to cease operation during "extreme flood conditions" at its Pedernales River crossing. Longhorn Partners must pay an outside contractor to test water quality at 12 locations in proximity to stream crossings and arrange alternate water supplies for municipalities and private water-well owners "that have sensitive groundwater resources" along the pipeline route.

The additional safety and mitigation measures will add "tens of millions" of dollars to the pipeline's total cost, partnership officials told OGJ Online.

Longhorn Partners has already installed a new state-of-the-art system that will monitor pipeline operations every few seconds around the clock. It measures volumes entering and exiting the pipeline, along with suction and discharge pressures at pump stations to detect any leakage.

Some of the mitigation measures also will improve the safety of two other pipelines that share the same corridor with Longhorn Pipeline along much of its route, officials said.

From 1995 through 1998, the partnership cleaned, tested, and upgraded the existing crude oil pipeline with new safety and environmental protections as part of its conversion. The line also was extended, including a 9-mile addition in the Houston area and a 250-mile stretch across West Texas to El Paso on the Mexican border.

A new spur was built from Crane to Odessa in the heart of the Permian Basin, Texas' main oil-producing area, where gasoline and other refined products typically cost 10-20�/gal more than in those areas directly served by Gulf Coast refineries.

The proposed pipeline would provide a method for Gulf Coast refiners to move large quantities of products at lower costs to West Texas. Proponents claim the cheaper supply of cleaner-burning motor fuels could help reduce the air pollution that has become a sensitive international issue between the border cities of El Paso and Juarez, Mexico.

Interconnections with other pipelines in West Texas could also move refined products into New Mexico and Arizona. That would relieve pressures on the California market since that state now exports large quantities of gasoline and diesel fuel into Arizona, proponents said.

Troubled legal history
But in 1998, several West Texas landowners filed a federal lawsuit against Longhorn Partners, the EPA and DOT to halt the proposed pipeline because of its alleged threat to the Edwards Aquifer. All but two of the landowners later withdrew from the suit, which was subsequently joined by the City of Austin, the Lower Colorado River Authority, the Barton Springs/Edwards Aquifer Conservation District, and others.

Media reports and statements by property owners who dropped out of the suit later indicated that the original lawsuit was funded by Navajo Refining Co. of Artesia, NM, that sells gasoline and diesel into the West Texas, New Mexico and Arizona markets. Longhorn Partners subsequently sued Navajo in state court for illegal interference with existing and prospective contracts and for anti-trust violations (OGJ, July 20, 1998, p. 36).

Meanwhile, the federal judge issued a temporary injunction against the pipeline. In 1999, parties to that original suit agreed to a voluntary environmental assessment jointly directed by EPA and DOT. As part of that study, an outside contractor analyzed 8,100 segments of the pipeline, checking for safety along its entire length.

A draft report of that assessment was released in October 1999 with a preliminary finding of no significant impact on the environment by the proposed pipeline.

If final judicial approval is granted by the federal judge, Longhorn Partners expects to open the pipeline by mid-2001.

Related Articles

Russia’s Turkey pipeline deal possibly may keep door to Europe ajar

12/18/2014 Russia’s memorandum of understanding to build a natural gas pipeline to Turkey after canceling its South Stream project could help keep the door op...

EPP kills plans for Bakken-to-Cushing crude oil pipeline

12/15/2014 Enterprise Products Partners LP (EPP) has elected not to proceed with development of its proposed crude oil pipeline that would have extended 1,200...

Kinder Morgan to deliver natural gas to Corpus Christi Liquefaction

12/11/2014 Kinder Morgan Inc. (KMI) companies Kinder Morgan Texas Pipeline, Kinder Morgan Tejas Pipeline, and Tennessee Gas Pipeline Co. (TGP) have entered in...

BG agrees to sale of Australian gas pipeline to APA Group

12/10/2014

BG Group PLC agreed to sell its wholly owned subsidiary Queensland Curtis LNG Pipeline Pty. Ltd. (QCLNG) to APA Group for about $5 billion.

More West Texas gathering, processing to come onstream

12/09/2014 EagleClaw Midstream Services LLC, Midland, Tex., has bought natural gas gathering and processing in Reeves County, Tex. The company declined to ide...

Methane controls just part of complete climate strategy, speakers say

12/08/2014 Reducing oil and gas operations’ methane emissions is an essential, but far from the only, part of a comprehensive climate strategy, speakers at a ...

Rail tank car rule could cost economy billions, report says

12/08/2014 The US Pipeline and Hazardous Materials Safety Administration's (PHMSA) proposed rail tank car rule could cost the US economy as much as $60 billio...

Renewed dilbit investigation faces similar hurdles of past debate

12/05/2014 A National Research Council committee opened a second investigation of potential environmental consequences from diluted bitumen (dilbit) spills fr...

Southwestern continues Marcellus expansion

12/03/2014 Southwestern Energy Co., Houston, has signed an agreement to purchase oil and gas assets, including 46,700 net acres, in northeast Pennsylvania fro...

White Papers

AVEVA NET Accesses and Manages the Digital Asset

Global demand for new process plants, power plants and infrastructure is increasing steadily with the ...
Sponsored by

AVEVA’s Approach for the Digital Asset

To meet the requirements for leaner project execution and more efficient operations while transferring...
Sponsored by

Diversification - the technology aspects

In tough times, businesses seek to diversify into adjacent markets or to apply their skills and resour...
Sponsored by

Engineering & Design for Lean Construction

Modern marketing rhetoric claims that, in order to cut out expensive costs and reduce risks during the...
Sponsored by

Object Lessons - Why control of engineering design at the object level is essential for efficient project execution

Whatever the task, there is usually only one way to do it right and many more to do it wrong. In the c...
Sponsored by

Plant Design for Lean Construction - at your fingertips

One area which can provide improvements to the adoption of Lean principles is the application of mobil...
Sponsored by

How to Keep Your Mud System Vibrator Hose from Getting Hammered to Death

To prevent the vibrating hoses on your oilfield mud circulation systems from failing, you must examine...
Sponsored by

Duty of Care

Good corporate social responsibility means implementing effective workplace health and safety measures...
Sponsored by

Available Webcasts


On Demand

Optimizing your asset management practices to mitigate the effects of a down market

Thu, Dec 11, 2014

The oil and gas market is in constant flux, and as the price of BOE (Barrel of Oil Equivalent) goes down it is increasingly important to optimize your asset management strategy to stay afloat.  Attend this webinar to learn how developing a solid asset management plan can help your company mitigate costs in any market.

register:WEBCAST


Parylene Conformal Coatings for the Oil & Gas Industry

Thu, Nov 20, 2014

In this concise 30-minute webinar, participants have an opportunity to learn more about how Parylene coatings are applied, their features, and the value they add to devices and components.

register:WEBCAST


Utilizing Predictive Analytics to Optimize Productivity in Oil & Gas Operations

Tue, Nov 18, 2014

Join IBM on Tuesday, November 18 @ 1pm CST to explore how Predictive Analytics can help your organization maximize productivity, operational performance & associated processes to drive enterprise wide productivity and profitability.

register:WEBCAST


US HYDROCARBON EXPORTS Part 3 — LNG

Fri, Nov 14, 2014

US LNG Exports, the third in a trilogy of webcasts focusing on the broad topic of US Hydrocarbon Exports.

A discussion of the problems and potential for the export of US-produced liquefied natural gas.

These and other topics will be discussed, with the latest thoughts on U.S. LNG export policy.

register:WEBCAST


Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected